1 Harrison St
San Francisco permit 202508153157 · Financial District/South Beach
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Defferred curtainwall: structural only submission assocated with approved pa 202410173107
- Filed
- Aug 29, 2025
- Issued
- Dec 23, 2025 (4 months after filing)
- Completed
- Oct 20, 2026 (10 months after issuance)
- Review stops
- 12 stops across 4 departments
- Comments issued
- Twice, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Aug 14, 2025 | Aug 28, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 29, 2025 | Aug 29, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Aug 29, 2025 | Oct 7, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 29, 2025 | Oct 7, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 29, 2025 | Dec 18, 2025 | Administrative |
Street use and mapping Public Works · DPW-BSM | Aug 29, 2025 | Sep 4, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Aug 29, 2025 | Dec 18, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Oct 30, 2025 | Nov 17, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Oct 30, 2025 | Nov 17, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 15, 2025 | Dec 17, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Dec 18, 2025 | Dec 18, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 18, 2025 | Dec 23, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $1
| Name | Role | License on permit |
|---|---|---|
| Joe Gulden | Engineer | S-5797 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026