San Francisco permit 202508153159 · Noe Valley

Legalize or fix a violationFull plan reviewApproved
Street view · Mar 2025
Google Street View of 260 Chattanooga St, Mar 2025
Scope of work
As written on the permit application.

Legalization of (e) ground fl unit @ rear of builg per ordinance 43-14. for a building total of (3) residential units.remove connecting interior stair;infill fl framing assembly to separate ground.entire ground fl to be sprinklered per information sheet fs-05 & eg-05.

Timeline
Key dates from the city record.
Filed
Jan 29, 2026
Issued
Not issued yet
Completed
Not completed yet
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
33 stops across 6 departments
Comments issued
9 times, by Permit Center, Building Inspection, Fire Department, Public Works
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Aug 25, 2025Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Jan 20, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Jan 29, 2026Administrative

Zoning review

Planning · CP-ZOC

Mar 3, 2026Approved

Building plan review

Building Inspection · BLDG

Mar 13, 2026Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Mar 13, 2026Not Applicable

Mechanical and energy plan review

Building Inspection · MECH

Feb 18, 2026Issued Comments

Fire Department housing review

Fire Department · SFFD-HQ

Feb 5, 2026Issued Comments

Street use and mapping

Public Works · DPW-BSM

Apr 16, 2026Approved

Urban forestry

Public Works · DPW-BUF

Mar 4, 2026Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Feb 9, 2026Approved

Permit Processing Center

Building Inspection · PPC

Aug 31, 2026Administrative

Public Utilities Commission review

Public Utilities · SFPUC

Apr 24, 2026Approved

Building plan review

Building Inspection · BLDG

Apr 24, 2026Issued Comments

Building plan review

Building Inspection · BLDG

Apr 29, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

May 7, 2026Approved

Fire Department housing review

Fire Department · SFFD-HQ

May 18, 2026Issued Comments

Zoning review

Planning · CP-ZOC

Jul 22, 2026Approved

Building plan review

Building Inspection · BLDG

Jun 22, 2026Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jun 25, 2026Approved

Fire Department housing review

Fire Department · SFFD-HQ

Jun 22, 2026Issued Comments

Street use and mapping

Public Works · DPW-BSM

Jun 15, 2026Approved

Urban forestry

Public Works · DPW-BUF

Jun 23, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jun 23, 2026Approved

Zoning review

Planning · CP-ZOC

Aug 3, 2026Approved

Building plan review

Building Inspection · BLDG

Aug 7, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

Aug 10, 2026Approved

Fire Department housing review

Fire Department · SFFD-HQ

Aug 19, 2026Approved

Street use and mapping

Public Works · DPW-BSM

Aug 3, 2026Approved

Urban forestry

Public Works · DPW-BUF

Aug 18, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

Aug 6, 2026Approved

Development fee collection

Building Inspection · DFCU

Aug 29, 2026Administrative

Central Permit Bureau

Building Inspection · CPB

In progressIn Progress

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Approved
Estimated cost
$180,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Serina L Calhoun

Syncopated Arch

ArchitectC30744
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202508153159 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record