260 Chattanooga St
San Francisco permit 202508153159 · Noe Valley
Legalization of (e) ground fl unit @ rear of builg per ordinance 43-14. for a building total of (3) residential units.remove connecting interior stair;infill fl framing assembly to separate ground.entire ground fl to be sprinklered per information sheet fs-05 & eg-05.
- Filed
- Jan 29, 2026
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 33 stops across 6 departments
- Comments issued
- 9 times, by Permit Center, Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Aug 13, 2025 | Aug 25, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Jan 6, 2026 | Jan 20, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 21, 2026 | Jan 29, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jan 29, 2026 | Mar 3, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 29, 2026 | Mar 13, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 29, 2026 | Mar 13, 2026 | Not Applicable |
Mechanical and energy plan review Building Inspection · MECH | Jan 29, 2026 | Feb 18, 2026 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Jan 29, 2026 | Feb 5, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jan 29, 2026 | Apr 16, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jan 29, 2026 | Mar 4, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 29, 2026 | Feb 9, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Jan 29, 2026 | Aug 31, 2026 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | Apr 20, 2026 | Apr 24, 2026 | Approved |
Building plan review Building Inspection · BLDG | Apr 24, 2026 | Apr 24, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Apr 29, 2026 | Apr 29, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 7, 2026 | May 7, 2026 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | May 11, 2026 | May 18, 2026 | Issued Comments |
Zoning review Planning · CP-ZOC | Jun 10, 2026 | Jul 22, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jun 10, 2026 | Jun 22, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 10, 2026 | Jun 25, 2026 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Jun 10, 2026 | Jun 22, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jun 10, 2026 | Jun 15, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jun 10, 2026 | Jun 23, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 10, 2026 | Jun 23, 2026 | Approved |
Zoning review Planning · CP-ZOC | Jul 31, 2026 | Aug 3, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jul 31, 2026 | Aug 7, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 31, 2026 | Aug 10, 2026 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Jul 31, 2026 | Aug 19, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 31, 2026 | Aug 3, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jul 31, 2026 | Aug 18, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 31, 2026 | Aug 6, 2026 | Approved |
Development fee collection Building Inspection · DFCU | Aug 19, 2026 | Aug 29, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Aug 31, 2026 | In progress | In Progress |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Approved
- Estimated cost
- $180,000
| Name | Role | License on permit |
|---|---|---|
| Serina L Calhoun Syncopated Arch | Architect | C30744 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025