4179 26th St
San Francisco permit 202508153192 · Noe Valley
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
New exit passageway through the (e) home in front for new rear yard adu. may share the same drawing of adu pa# 202508062456.
- Filed
- Aug 26, 2025
- Issued
- Mar 10, 2026 (6 months after filing)
- Completed
- Aug 18, 2026 (5 months after issuance)
- Review stops
- 46 stops across 6 departments
- Comments issued
- 11 times, by Building Inspection, Public Works, Public Utilities, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Aug 1, 2025 | Aug 13, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 27, 2025 | Aug 27, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Aug 27, 2025 | Oct 29, 2025 | Not Applicable |
Building plan review Building Inspection · BLDG | Aug 27, 2025 | Sep 15, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 27, 2025 | Sep 26, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 27, 2025 | Sep 5, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 27, 2025 | Sep 2, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 27, 2025 | Sep 8, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Aug 27, 2025 | Oct 6, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 27, 2025 | Aug 28, 2025 | Issued Comments |
Public Utilities programs review Public Utilities · SFPUC-PRG | Aug 27, 2025 | Sep 11, 2025 | Not Applicable |
Permit Processing Center Building Inspection · PPC | Aug 27, 2025 | Mar 3, 2026 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | Sep 3, 2025 | Sep 3, 2025 | Approved |
Mechanical plan review quality control Building Inspection · MECH-QC | Sep 5, 2025 | Sep 5, 2025 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Sep 12, 2025 | Sep 12, 2025 | Approved |
Building plan review Building Inspection · BLDG | Oct 28, 2025 | Nov 7, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Oct 28, 2025 | Nov 7, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 28, 2025 | Nov 21, 2025 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Oct 28, 2025 | Oct 29, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Oct 28, 2025 | Oct 29, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Oct 28, 2025 | Nov 10, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Oct 28, 2025 | Oct 29, 2025 | Approved |
Public Utilities programs review Public Utilities · SFPUC-PRG | Oct 28, 2025 | Nov 7, 2025 | Not Applicable |
Building plan review Building Inspection · BLDG | Dec 3, 2025 | Dec 4, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Dec 3, 2025 | Dec 12, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 3, 2025 | Dec 9, 2025 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Dec 3, 2025 | Dec 8, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 3, 2025 | Dec 9, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Dec 3, 2025 | Dec 22, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Dec 3, 2025 | Dec 4, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jan 13, 2026 | Jan 14, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jan 13, 2026 | Jan 23, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 13, 2026 | Jan 21, 2026 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Jan 13, 2026 | Jan 23, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 13, 2026 | Jan 15, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jan 13, 2026 | Jan 26, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 13, 2026 | Jan 15, 2026 | Approved |
Development fee collection Building Inspection · DFCU | Jan 30, 2026 | Jan 30, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Feb 10, 2026 | Feb 12, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Feb 10, 2026 | Feb 18, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 10, 2026 | Feb 12, 2026 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Feb 10, 2026 | Feb 13, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 10, 2026 | Feb 11, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Feb 10, 2026 | Mar 2, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 10, 2026 | Feb 13, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 3, 2026 | Mar 10, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $32,524
| Name | Role | License on permit |
|---|---|---|
| Venkata Rohit Grandhi Venkata Rohit Grandhi, P.E. | Engineer | C88709 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025