664 45th Av
San Francisco permit 202508183278 · Outer Richmond
Erect a new two dwelling unit with no basement, detached adu in compliance with state adu regulations per plannign code section 207.2.type v
- Filed
- Sep 4, 2025
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 29 stops across 6 departments
- Comments issued
- 4 times, by Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Aug 14, 2025 | Sep 3, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 4, 2025 | Sep 5, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Sep 5, 2025 | Oct 8, 2025 | Approved |
Building plan review Building Inspection · BLDG | Sep 5, 2025 | Sep 23, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Sep 5, 2025 | Sep 18, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Sep 5, 2025 | Sep 17, 2025 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Sep 5, 2025 | Sep 8, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 5, 2025 | Sep 8, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Sep 5, 2025 | Oct 2, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 5, 2025 | Sep 5, 2025 | Approved |
Public Utilities programs review Public Utilities · SFPUC-PRG | Sep 5, 2025 | Sep 11, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Sep 5, 2025 | Nov 5, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Oct 14, 2025 | Oct 14, 2025 | Approved |
Building plan review Building Inspection · BLDG | Oct 14, 2025 | Oct 20, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 14, 2025 | Oct 20, 2025 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Oct 14, 2025 | Oct 20, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 14, 2025 | Oct 15, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Oct 14, 2025 | Oct 24, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 14, 2025 | Oct 21, 2025 | Approved |
Public Utilities programs review Public Utilities · SFPUC-PRG | Oct 14, 2025 | Oct 14, 2025 | Approved |
Zoning review Planning · CP-ZOC | Oct 24, 2025 | Oct 29, 2025 | Approved |
Building plan review Building Inspection · BLDG | Oct 24, 2025 | Oct 24, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 24, 2025 | Oct 27, 2025 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Oct 24, 2025 | Oct 28, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 24, 2025 | Oct 27, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 24, 2025 | Oct 31, 2025 | Approved |
Public Utilities programs review Public Utilities · SFPUC-PRG | Oct 24, 2025 | Oct 31, 2025 | Approved |
Development fee collection Building Inspection · DFCU | Nov 3, 2025 | Nov 4, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Nov 5, 2025 | In progress | In Progress |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Approved
- Estimated cost
- $563,271
| Name | Role | License on permit |
|---|---|---|
| Della Tran Duane Tran | Engineer | 91229 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025