443 Campbell Av
San Francisco permit 202508193323 · Visitacion Valley
Two story addition to the rear. re-arrange top floor layout. add one full bathroom. re-arrange ground flr with one recreation room, bedroom, and one bath. new two level deck and stair to rear yard.
- Filed
- Jan 4, 2026
- Issued
- Aug 20, 2026 (7 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).
- Review stops
- 35 stops across 6 departments
- Comments issued
- 15 times, by Permit Center, Building Inspection, Fire Department, Public Works, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Aug 17, 2025 | Sep 3, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Sep 29, 2025 | Oct 9, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 14, 2025 | Jan 5, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jan 5, 2026 | Jan 7, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 5, 2026 | Feb 12, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 5, 2026 | Feb 12, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 5, 2026 | Jan 23, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 5, 2026 | Jan 19, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jan 5, 2026 | Jan 6, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 5, 2026 | Jan 12, 2026 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Jan 5, 2026 | Aug 13, 2026 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | Jan 15, 2026 | Jan 20, 2026 | Approved |
Zoning review Planning · CP-ZOC | May 20, 2026 | May 22, 2026 | Approved |
Building plan review Building Inspection · BLDG | May 20, 2026 | Jun 2, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | May 20, 2026 | Jun 2, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 20, 2026 | May 22, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 20, 2026 | May 29, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | May 20, 2026 | May 21, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | May 20, 2026 | May 21, 2026 | Approved |
Zoning review Planning · CP-ZOC | Jun 16, 2026 | Jun 16, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jun 16, 2026 | Jun 18, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jun 16, 2026 | Jun 18, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 16, 2026 | Jun 22, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jun 16, 2026 | Jun 29, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 16, 2026 | Jun 17, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jun 16, 2026 | Jun 23, 2026 | Approved |
Zoning review Planning · CP-ZOC | Jul 7, 2026 | Jul 8, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jul 7, 2026 | Jul 9, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jul 7, 2026 | Jul 9, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 7, 2026 | Jul 8, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jul 7, 2026 | Jul 16, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 7, 2026 | Jul 9, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jul 7, 2026 | Jul 15, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 10, 2026 | Aug 12, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 13, 2026 | Aug 20, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $418,000
| Name | Role | License on permit |
|---|---|---|
| Jin Qing Li J. Li & Associates | Engineer | C47534 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Nov 2020