300 Salinas Av
San Francisco permit 202508193333 · Bayview Hunters Point
To comply with nov# 202426665, agreed in hearing to cover existing seismic braces in public right-of-way with an enclosure. planter bed was rejected due to public loitering in the planter bed. this solution was endorsed. we're also submitting minor sidewalk encroachment permit with this application.
- Filed
- Sep 9, 2025
- Issued
- Jan 22, 2026 (4 months after filing)
- Completed
- Feb 23, 2026 (1 month after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 14 stops across 5 departments
- Comments issued
- Twice, by Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Aug 18, 2025 | Sep 5, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 5, 2025 | Sep 10, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Sep 10, 2025 | Oct 14, 2025 | Approved |
Building plan review Building Inspection · BLDG | Sep 10, 2025 | Oct 14, 2025 | Approved-Stipulated |
Structural plan approval Building Inspection · PAD-STR | Sep 10, 2025 | Oct 14, 2025 | Not Applicable |
Fire prevention review Fire Department · SFFD | Sep 10, 2025 | Sep 23, 2025 | Not Applicable |
Street use and mapping Public Works · DPW-BSM | Sep 10, 2025 | Oct 14, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Sep 10, 2025 | Jan 8, 2026 | Administrative |
Street use and mapping Public Works · DPW-BSM | Oct 22, 2025 | Oct 22, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Jan 6, 2026 | Jan 6, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 6, 2026 | Jan 8, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 6, 2026 | Jan 6, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 8, 2026 | Jan 22, 2026 | Administrative |
Code enforcement Building Inspection · CES | Jan 21, 2026 | Jan 21, 2026 | Approved |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $30,000
| Name | Role | License on permit |
|---|---|---|
| James H Neubert James Neubert Architects | Architect | C-27271 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2022