2424 Mariposa St
San Francisco permit 202508193353 · Mission
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
New ramp and stair accessibility upgrades @ building front entry to comply with disabled access requirements; current scope is for completion of proposed accessibility upgrades under pa# 201412184013 &201503201456 (rev to 201412184013) was not completed.
- Filed
- Sep 30, 2025
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 23 stops across 5 departments
- Comments issued
- 6 times, by Permit Center, Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Aug 18, 2025 | Sep 4, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Sep 11, 2025 | Sep 25, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 25, 2025 | Sep 30, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Sep 30, 2025 | Oct 1, 2025 | Approved |
Building plan review Building Inspection · BLDG | Sep 30, 2025 | Nov 13, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Sep 30, 2025 | Oct 29, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 30, 2025 | Oct 27, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Sep 30, 2025 | Jan 2, 2026 | Not Applicable |
Street use and mapping Public Works · DPW-BSM | Sep 30, 2025 | Oct 2, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Sep 30, 2025 | In progress | — |
Building plan review quality control Building Inspection · BLDG-QC | Nov 13, 2025 | Nov 14, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 12, 2025 | Dec 16, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Dec 15, 2025 | Dec 15, 2025 | Approved |
Building plan review Building Inspection · BLDG | Dec 18, 2025 | May 21, 2026 | Issued Comments |
Building plan review quality control Building Inspection · BLDG-QC | Dec 19, 2025 | Dec 19, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Dec 22, 2025 | Dec 22, 2025 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | May 20, 2026 | May 20, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 1, 2026 | Jun 3, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jun 5, 2026 | Jun 10, 2026 | Approved |
Zoning review Planning · CP-ZOC | Jun 8, 2026 | Jun 15, 2026 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Jun 9, 2026 | In progress | In Progress |
Mechanical and energy plan review Building Inspection · MECH | Jun 12, 2026 | Jun 12, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $150,000
| Name | Role | License on permit |
|---|---|---|
| Michael Alan Garavaglia Garavaglia Architecture | Architect | C-14833 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026