3821 Noriega St
San Francisco permit 202508203491 · Sunset/Parkside
Change of use and occupancy from m to b. interior remodel to existing +/- 2000 sf market to accomodate a bar and restaurant.
- Filed
- Aug 20, 2025
- Issued
- Oct 7, 2025 (2 months after filing)
- Completed
- Mar 27, 2026 (6 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2025 were typically issued within 1 month (median of 5,178 issued permits).
- Review stops
- 19 stops across 5 departments
- Comments issued
- 5 times, by Building Inspection, Fire Department, Public Health
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Aug 20, 2025 | Aug 20, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Aug 20, 2025 | Aug 20, 2025 | Approved |
Building plan review Building Inspection · BLDG | Aug 20, 2025 | Aug 20, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 20, 2025 | Aug 20, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 21, 2025 | Aug 21, 2025 | Not Applicable |
Building plan review Building Inspection · BLDG | Aug 22, 2025 | Aug 22, 2025 | Approved |
Public health review Public Health · HEALTH | Aug 22, 2025 | Aug 22, 2025 | Administrative |
Public health food review Public Health · HEALTH-FD | Aug 22, 2025 | Aug 22, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 29, 2025 | Aug 29, 2025 | Issued Comments |
Public health food review Public Health · HEALTH-FD | Aug 29, 2025 | Aug 29, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 3, 2025 | Sep 3, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Sep 3, 2025 | Sep 3, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 3, 2025 | Sep 3, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Sep 5, 2025 | Sep 5, 2025 | Approved |
Intake Building Inspection · INTAKE | Sep 26, 2025 | Sep 26, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Sep 26, 2025 | Sep 26, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Sep 26, 2025 | Sep 26, 2025 | Approved |
Building plan review Building Inspection · BLDG | Oct 3, 2025 | Oct 3, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 7, 2025 | Oct 7, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $231,000
| Name | Role | License on permit |
|---|---|---|
| Dane William Bunton Banna Architecture | Architect | c36022 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2015