716 Montgomery St
San Francisco permit 202508203506 · Chinatown
Studio b - bring (e) stair case to mezzanine to code extending mezz area, remodel bathroom, (n) electrical lighting, new wood floors and carpet, paint, (n) a/c unit
- Filed
- Aug 20, 2025
- Issued
- Feb 11, 2026 (6 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2025 were typically issued within 1 month (median of 5,178 issued permits).
- Review stops
- 18 stops across 4 departments
- Comments issued
- 3 times, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Aug 20, 2025 | Aug 20, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Aug 20, 2025 | Aug 20, 2025 | Not Applicable |
Intake Building Inspection · INTAKE | Sep 24, 2025 | Sep 24, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Sep 24, 2025 | Sep 24, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Sep 24, 2025 | Sep 24, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Sep 24, 2025 | Sep 24, 2025 | Issued Comments |
Intake Building Inspection · INTAKE | Dec 17, 2025 | Dec 17, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Dec 17, 2025 | Dec 17, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Dec 17, 2025 | Dec 17, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 19, 2025 | Dec 19, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Dec 19, 2025 | Dec 19, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Dec 19, 2025 | Dec 19, 2025 | Not Applicable |
Public Utilities Commission review Public Utilities · SFPUC | Dec 19, 2025 | Dec 19, 2025 | Approved |
Intake Building Inspection · INTAKE | Jan 29, 2026 | Jan 29, 2026 | Administrative |
Intake Building Inspection · INTAKE | Feb 3, 2026 | Feb 3, 2026 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Feb 3, 2026 | Feb 3, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | Feb 3, 2026 | Feb 3, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 11, 2026 | Feb 11, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $62,500
| Name | Role | License on permit |
|---|---|---|
| Alan Mark Waldman | Engineer | C38905 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026