1360 Wayland St
San Francisco permit 202508203521 · Portola
3rd floor addtion to an existing 2-story sfr subject to sec311 (site permit) planning/ design review process. rooftop pv solar system. new elevator to servce all floors. interior remodel of existing floors. pv system at roof.
- Filed
- Aug 27, 2025
- Issued
- Mar 6, 2026 (6 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 39 stops across 6 departments
- Comments issued
- 14 times, by Building Inspection, Fire Department, Public Works, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Aug 19, 2025 | Aug 27, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 27, 2025 | Aug 28, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Aug 28, 2025 | Dec 9, 2025 | Approved |
Building plan review Building Inspection · BLDG | Aug 28, 2025 | Sep 16, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 28, 2025 | Sep 21, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 28, 2025 | Oct 17, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 28, 2025 | Sep 5, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 28, 2025 | Sep 8, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Aug 28, 2025 | Sep 26, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 28, 2025 | Sep 2, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Aug 28, 2025 | Feb 24, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Dec 8, 2025 | Dec 11, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Dec 8, 2025 | Dec 24, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 8, 2025 | Dec 12, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 8, 2025 | Dec 12, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Dec 8, 2025 | Dec 9, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Dec 8, 2025 | Dec 23, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Dec 8, 2025 | Dec 16, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Dec 12, 2025 | Jan 2, 2026 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Dec 31, 2025 | Dec 31, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jan 12, 2026 | Jan 15, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 12, 2026 | Jan 15, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jan 12, 2026 | Jan 23, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 12, 2026 | Jan 16, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | Jan 12, 2026 | Jan 12, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jan 12, 2026 | Jan 22, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 12, 2026 | Jan 14, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jan 12, 2026 | Jan 29, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 12, 2026 | Jan 13, 2026 | Approved |
Zoning review Planning · CP-ZOC | Feb 2, 2026 | Feb 4, 2026 | Approved |
Building plan review Building Inspection · BLDG | Feb 2, 2026 | Feb 5, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Feb 2, 2026 | Feb 9, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 2, 2026 | Feb 3, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | Feb 2, 2026 | Feb 11, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Feb 2, 2026 | Feb 6, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 2, 2026 | Feb 3, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Feb 2, 2026 | Feb 17, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 2, 2026 | Feb 6, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 24, 2026 | Mar 6, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $631,392
| Name | Role | License on permit |
|---|---|---|
| Mark Elliott Bucciarelli Baukunst | Architect | 23159 |
| Nilgun Asci Wolpe Ny Engineering Consulting | Engineer | 68482 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2019