1300 09th Av
San Francisco permit 202508213635 · Inner Sunset
T.i. of e) gutted restaurant space for new restaurant. work included install of all new food service equipment, partial updated interior, finishes thru, demo of 1 e) walk-in cooler ( w/ infill/patch remaining) no exterior work
- Filed
- Aug 21, 2025
- Issued
- Oct 9, 2025 (2 months after filing)
- Completed
- Jan 13, 2026 (3 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2025 were typically issued within 1 month (median of 5,178 issued permits).
- Review stops
- 18 stops across 5 departments
- Comments issued
- 6 times, by Building Inspection, Public Health
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Aug 21, 2025 | Aug 21, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Aug 21, 2025 | Aug 21, 2025 | Approved |
Building plan review Building Inspection · BLDG | Aug 21, 2025 | Aug 21, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 21, 2025 | Aug 21, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Aug 21, 2025 | Aug 21, 2025 | Issued Comments |
Intake Building Inspection · INTAKE | Sep 23, 2025 | Sep 23, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Sep 23, 2025 | Sep 23, 2025 | Approved |
Building plan review Building Inspection · BLDG | Sep 23, 2025 | Sep 23, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 23, 2025 | Sep 23, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Sep 23, 2025 | Sep 23, 2025 | Not Applicable |
Public Utilities Commission review Public Utilities · SFPUC | Sep 23, 2025 | Sep 23, 2025 | Approved |
Public health review Public Health · HEALTH | Sep 23, 2025 | Sep 23, 2025 | Administrative |
Public health food review Public Health · HEALTH-FD | Sep 23, 2025 | Sep 23, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Sep 30, 2025 | Sep 30, 2025 | Issued Comments |
Public health food review Public Health · HEALTH-FD | Sep 30, 2025 | Sep 30, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Oct 8, 2025 | Oct 8, 2025 | Approved |
Public health food review Public Health · HEALTH-FD | Oct 8, 2025 | Oct 8, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 9, 2025 | Oct 9, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $89,520
| Name | Role | License on permit |
|---|---|---|
| Stuart David Hills Apparatus | Architect | C24966 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026