3 Topaz Wy
San Francisco permit 202508213676 · Glen Park
Selective demo portion of level 1 & 2 decks as needed for access of 1 topaz work to install footings, post & lvl framing reconnect level 1 & 2 decks joists to new post & lvl framing. repair or replace wood rot to wind walls joists, decking, railings & patch in new wood shingle siding.
- Filed
- Aug 21, 2025
- Issued
- Oct 3, 2025 (1 month after filing)
- Completed
- Apr 7, 2026 (6 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 9 stops across 2 departments
- Comments issued
- Once, by Planning
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 21, 2025 | Aug 22, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Aug 22, 2025 | Aug 26, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 22, 2025 | Aug 25, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Aug 22, 2025 | Sep 24, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Sep 15, 2025 | Sep 15, 2025 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Sep 15, 2025 | Sep 15, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Sep 19, 2025 | Sep 19, 2025 | Approved |
Building plan review Building Inspection · BLDG | Sep 19, 2025 | Sep 19, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 24, 2025 | Oct 3, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $2,500
| Name | Role | License on permit |
|---|---|---|
| David A Kesler David Kesler Architect | Architect | C28122 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026