Scope of work
As written on the permit application.

Rev 201908229595. additionally, units 1, 2, 3 and 4 relocation of kitchens, addition of 2 bathrooms, relocation of 4 existing bathrooms and general seismic upgrade. replacement of all existing windows with vynil windows of matching configuration and operation

Timeline
Key dates from the city record.
Filed
Sep 10, 2025
Issued
Feb 2, 2026 (5 months after filing)
Completed
Oct 13, 2026 (8 months after issuance)
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
32 stops across 5 departments
Comments issued
7 times, by Building Inspection
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Sep 10, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Sep 10, 2025Administrative

Zoning review

Planning · CP-ZOC

Sep 11, 2025Approved

Building plan review

Building Inspection · BLDG

Oct 22, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Oct 12, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Oct 16, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

Dec 8, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Sep 16, 2025Approved

Permit Processing Center

Building Inspection · PPC

Jan 27, 2026Administrative

Zoning review

Planning · CP-ZOC

Dec 9, 2025Approved

Building plan review

Building Inspection · BLDG

Nov 18, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Nov 20, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Nov 20, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Nov 14, 2025Approved

Building plan review

Building Inspection · BLDG

Dec 10, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Dec 5, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Dec 18, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Dec 5, 2025Approved

Zoning review

Planning · CP-ZOC

Dec 24, 2025Approved

Building plan review

Building Inspection · BLDG

Jan 8, 2026Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Jan 5, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

Dec 30, 2025Approved

Fire prevention review

Fire Department · SFFD

Dec 23, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Dec 26, 2025Approved

Building plan review

Building Inspection · BLDG

Jan 13, 2026Approved

Zoning review

Planning · CP-ZOC

Jan 27, 2026Approved

Building plan review

Building Inspection · BLDG

Jan 21, 2026Approved

Structural plan approval

Building Inspection · PAD-STR

Jan 22, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

Jan 21, 2026Approved

Fire prevention review

Fire Department · SFFD

Jan 23, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jan 22, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Feb 2, 2026Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$467,902
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Gary S Varum

Gary S. Varum S.E.

EngineerS3305
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202508223726 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record