73 Fountain St
San Francisco permit 202508223731 · Noe Valley
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Revision to pa2020-0113-1721 installed hardy boards instead of hardy shingles on front elevation; installed horizontal railing instead of vertical; changed the arch on top of front porch. want the plans to reflect the changes in the railings and shingles
- Filed
- Aug 22, 2025
- Issued
- Aug 28, 2025 (within 1 month of filing)
- Completed
- Oct 28, 2025 (2 months after issuance)
- Review stops
- 4 stops across 2 departments
- Comments issued
- None
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Aug 22, 2025 | Aug 22, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Aug 22, 2025 | Aug 22, 2025 | Approved |
Building plan review Building Inspection · BLDG | Aug 22, 2025 | Aug 22, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 28, 2025 | Aug 28, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $1,000
| Name | Role | License on permit |
|---|---|---|
| Luis Rodriguez Innovative Design | Architect | 87060 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2023