CheckMyDesigner

4390 Cesar Chavez St

San Francisco permit 202508253806 · Noe Valley

Home remodelFull plan reviewIssued
Street view · Feb 2022
Google Street View of 4390 Cesar Chavez St, Feb 2022
Scope of work
As written on the permit application.

Add bathroom to crawl space, add kitchenette to basement. foundation & structural work per plans. electrical & plumbing work to be carried out. adding new laundry in crawl space.

Timeline
Key dates from the city record.
Filed
Jan 20, 2026
Issued
Jul 15, 2026 (6 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
25 stops across 5 departments
Comments issued
5 times, by Permit Center, Building Inspection
Review stopFinishedResult

Intake

Building Inspection · INTAKE

Aug 25, 2025Administrative

Zoning review

Planning · CP-ZOC

Aug 25, 2025Approved

Intake

Building Inspection · INTAKE

Dec 4, 2025Administrative

Permit Center

Permit Center · PERMIT-CTR

Dec 26, 2025Issued Comments

Central Permit Bureau

Building Inspection · CPB

Jan 21, 2026Administrative

Permit Center

Permit Center · PERMIT-CTR

Jan 16, 2026Approved

Zoning review

Planning · CP-ZOC

Jan 21, 2026Approved

Building plan review

Building Inspection · BLDG

Mar 9, 2026Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Mar 10, 2026Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Mar 9, 2026Issued Comments

Fire prevention review

Fire Department · SFFD

Jan 30, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

Feb 11, 2026Approved

Permit Processing Center

Building Inspection · PPC

May 19, 2026Administrative

Zoning review

Planning · CP-ZOC

Mar 20, 2026Approved

Building plan review

Building Inspection · BLDG

Mar 26, 2026Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Mar 26, 2026Not Applicable

Mechanical and energy plan review

Building Inspection · MECH

Mar 23, 2026Approved

Fire prevention review

Fire Department · SFFD

Mar 26, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

Mar 30, 2026Approved

Zoning review

Planning · CP-ZOC

Apr 30, 2026Approved

Building plan review

Building Inspection · BLDG

May 19, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

Apr 30, 2026Approved

Fire prevention review

Fire Department · SFFD

May 6, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

May 1, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Jul 15, 2026Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$222,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Ryan G Morris

Morris Architecture

ArchitectC33359
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202508253806 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record