4390 Cesar Chavez St
San Francisco permit 202508253806 · Noe Valley
Add bathroom to crawl space, add kitchenette to basement. foundation & structural work per plans. electrical & plumbing work to be carried out. adding new laundry in crawl space.
- Filed
- Jan 20, 2026
- Issued
- Jul 15, 2026 (6 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).
- Review stops
- 25 stops across 5 departments
- Comments issued
- 5 times, by Permit Center, Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Aug 25, 2025 | Aug 25, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Aug 25, 2025 | Aug 25, 2025 | Approved |
Intake Building Inspection · INTAKE | Dec 4, 2025 | Dec 4, 2025 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Dec 4, 2025 | Dec 26, 2025 | Issued Comments |
Central Permit Bureau Building Inspection · CPB | Dec 8, 2025 | Jan 21, 2026 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Jan 6, 2026 | Jan 16, 2026 | Approved |
Zoning review Planning · CP-ZOC | Jan 21, 2026 | Jan 21, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 21, 2026 | Mar 9, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 21, 2026 | Mar 10, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 21, 2026 | Mar 9, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 21, 2026 | Jan 30, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 21, 2026 | Feb 11, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Jan 21, 2026 | May 19, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Mar 20, 2026 | Mar 20, 2026 | Approved |
Building plan review Building Inspection · BLDG | Mar 20, 2026 | Mar 26, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Mar 20, 2026 | Mar 26, 2026 | Not Applicable |
Mechanical and energy plan review Building Inspection · MECH | Mar 20, 2026 | Mar 23, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Mar 20, 2026 | Mar 26, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 20, 2026 | Mar 30, 2026 | Approved |
Zoning review Planning · CP-ZOC | Apr 28, 2026 | Apr 30, 2026 | Approved |
Building plan review Building Inspection · BLDG | Apr 28, 2026 | May 19, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 28, 2026 | Apr 30, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Apr 28, 2026 | May 6, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 28, 2026 | May 1, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | May 19, 2026 | Jul 15, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $222,000
| Name | Role | License on permit |
|---|---|---|
| Ryan G Morris Morris Architecture | Architect | C33359 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2022