4546 19th St
San Francisco permit 202508274027 · Castro/Upper Market
Demo interior window walls @ foyer (to be replaced w/guardrail). new roof over atrium w/12 skylights. new leveled flr @ atrium. add gas fireplace appliance @ east wall. add new electric in newly enclosed space. refinish (e) walls w/new drywall finish. extend (e) rear deck 4'-3", fully cantilevered.
- Filed
- Sep 29, 2025
- Issued
- Apr 3, 2026 (6 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 19 stops across 4 departments
- Comments issued
- 4 times, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Aug 22, 2025 | Sep 12, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 12, 2025 | Sep 30, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Sep 30, 2025 | Oct 1, 2025 | Approved |
Building plan review Building Inspection · BLDG | Sep 30, 2025 | Nov 6, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Sep 30, 2025 | Nov 6, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Sep 30, 2025 | Oct 30, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 30, 2025 | Oct 1, 2025 | Approved-Stipulated |
Permit Processing Center Building Inspection · PPC | Sep 30, 2025 | Mar 11, 2026 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Jan 8, 2026 | Jan 8, 2026 | Issued Comments |
Zoning review Planning · CP-ZOC | Jan 13, 2026 | Jan 15, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 13, 2026 | Jan 23, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 13, 2026 | Jan 21, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jan 13, 2026 | Jan 22, 2026 | Approved-Stipulated |
Zoning review Planning · CP-ZOC | Jan 30, 2026 | Feb 5, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 30, 2026 | Feb 9, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 30, 2026 | Feb 4, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jan 30, 2026 | Feb 2, 2026 | Approved-Stipulated |
Fire prevention review Fire Department · SFFD | Feb 3, 2026 | Feb 5, 2026 | Approved-Stipulated |
Central Permit Bureau Building Inspection · CPB | Mar 11, 2026 | Apr 3, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $73,660
| Name | Role | License on permit |
|---|---|---|
| Christopher P Mcmahon Mcmahon Architects + Studio | Architect | C-22982 |
| Marcus Yan Sf Bay Engineering | Engineer | C-83553 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025