4355 Anza St
San Francisco permit 202508284114 · Outer Richmond
Ground floor change of use: change 1st flr piano studio to childcare center. (3-months to 2-year old, 22 kids). 2nd flr new laundry.
- Filed
- Sep 19, 2025
- Issued
- Apr 15, 2026 (7 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 48 stops across 6 departments
- Comments issued
- 14 times, by Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Aug 27, 2025 | Sep 17, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 17, 2025 | Sep 19, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Sep 19, 2025 | Oct 6, 2025 | Approved |
Building plan review Building Inspection · BLDG | Sep 19, 2025 | Oct 16, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Sep 19, 2025 | Oct 23, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 19, 2025 | Oct 24, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Sep 19, 2025 | Oct 7, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 19, 2025 | Dec 21, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 19, 2025 | Sep 29, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 19, 2025 | Sep 29, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Sep 19, 2025 | Mar 26, 2026 | Administrative |
Building plan review quality control Building Inspection · BLDG-QC | Oct 16, 2025 | Oct 16, 2025 | Approved |
Building plan review Building Inspection · BLDG | Oct 17, 2025 | Oct 17, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Nov 18, 2025 | Dec 4, 2025 | Approved |
Building plan review Building Inspection · BLDG | Nov 18, 2025 | Dec 10, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Nov 18, 2025 | Nov 26, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 18, 2025 | Nov 26, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Nov 18, 2025 | Nov 18, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Nov 18, 2025 | Nov 19, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Nov 18, 2025 | Nov 24, 2025 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Dec 10, 2025 | Dec 10, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jan 22, 2026 | Feb 10, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 22, 2026 | Feb 6, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 22, 2026 | Feb 2, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 22, 2026 | Jan 27, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | Jan 22, 2026 | Jan 22, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jan 22, 2026 | Jan 26, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jan 22, 2026 | Jan 23, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 22, 2026 | Jan 23, 2026 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Feb 6, 2026 | Feb 6, 2026 | Approved |
Zoning review Planning · CP-ZOC | Feb 26, 2026 | Feb 27, 2026 | Approved |
Building plan review Building Inspection · BLDG | Feb 26, 2026 | Mar 10, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Feb 26, 2026 | Mar 10, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 26, 2026 | Mar 5, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | Feb 26, 2026 | Feb 27, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Feb 26, 2026 | Mar 5, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 26, 2026 | Feb 27, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 26, 2026 | Mar 5, 2026 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Mar 10, 2026 | Mar 10, 2026 | Approved |
Zoning review Planning · CP-ZOC | Mar 13, 2026 | Mar 25, 2026 | Approved |
Building plan review Building Inspection · BLDG | Mar 13, 2026 | Mar 20, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 13, 2026 | Mar 20, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | Mar 13, 2026 | Mar 13, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Mar 13, 2026 | Mar 18, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 13, 2026 | Mar 19, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 13, 2026 | Mar 18, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Mar 20, 2026 | Mar 20, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 26, 2026 | Apr 15, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $281,098
| Name | Role | License on permit |
|---|---|---|
| Jin Qing Li J&S Consultant Inc | Engineer | 47534 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025