242 Lobos St
San Francisco permit 202509024405 · Oceanview/Merced/Ingleside
Remove back sunroom. install code comliant deck. lower half of resdience - change to legal adu. to comply with nov 202421854.
- Filed
- Dec 24, 2025
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 32 stops across 6 departments
- Comments issued
- 9 times, by Permit Center, Building Inspection, Fire Department, Public Works, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Aug 29, 2025 | Sep 18, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Nov 13, 2025 | Dec 2, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 24, 2025 | Dec 24, 2025 | Administrative |
Permit Processing Center Building Inspection · PPC | Dec 24, 2025 | In progress | Administrative |
Zoning review Planning · CP-ZOC | Dec 26, 2025 | Dec 29, 2025 | Approved |
Building plan review Building Inspection · BLDG | Dec 26, 2025 | Feb 3, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Dec 26, 2025 | Feb 3, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 26, 2025 | Jan 9, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 26, 2025 | Jan 8, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Dec 26, 2025 | Dec 30, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Dec 26, 2025 | Jan 5, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Dec 26, 2025 | Jan 6, 2026 | Approved |
Zoning review Planning · CP-ZOC | Apr 27, 2026 | Apr 29, 2026 | Approved |
Building plan review Building Inspection · BLDG | Apr 27, 2026 | May 18, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Apr 27, 2026 | May 14, 2026 | Not Applicable |
Mechanical and energy plan review Building Inspection · MECH | Apr 27, 2026 | May 5, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Apr 27, 2026 | Apr 29, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 27, 2026 | Apr 29, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Apr 27, 2026 | May 31, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 27, 2026 | May 6, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 7, 2026 | May 7, 2026 | Approved |
Zoning review Planning · CP-ZOC | Jun 18, 2026 | Jun 25, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jun 18, 2026 | Jun 30, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 18, 2026 | Jul 2, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jun 18, 2026 | Jun 22, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 18, 2026 | Jul 7, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jun 18, 2026 | Jul 21, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 18, 2026 | Jun 25, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jun 24, 2026 | Jun 29, 2026 | Approved |
Development fee collection Building Inspection · DFCU | Jul 22, 2026 | Jul 22, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jul 22, 2026 | In progress | In Progress |
Address verification Building Inspection · ADDR | Aug 3, 2026 | Aug 3, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $140,000
| Name | Role | License on permit |
|---|---|---|
| Amin Ghafooripour Padir Consulting Engineers | Engineer | C84986 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025