101 Gough St
San Francisco permit 202509044548 · Hayes Valley
Rehabilitation of 21 (e) units & provide 2 new dwelling units including new bathrooms & kitchens.provide new accessible entry and lobby, new finishes throughout, new hvac, plumbing system, electrical system and structural upgrades.
- Filed
- Nov 18, 2025
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 50 stops across 7 departments
- Comments issued
- 14 times, by Permit Center, CON, Planning, Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Aug 29, 2025 | Sep 16, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Oct 31, 2025 | Nov 14, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 18, 2025 | Nov 18, 2025 | Administrative |
Permit Processing Center Building Inspection · PPC | Nov 18, 2025 | Aug 27, 2026 | Administrative |
CON CON-BOND | Nov 19, 2025 | Nov 20, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Nov 19, 2025 | Nov 25, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 19, 2025 | Dec 17, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Nov 19, 2025 | Dec 11, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 19, 2025 | Nov 25, 2025 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Nov 19, 2025 | Dec 5, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Nov 19, 2025 | Nov 24, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Nov 19, 2025 | Dec 19, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Nov 19, 2025 | Dec 22, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Nov 25, 2025 | Jan 2, 2026 | Issued Comments |
Building plan review quality control Building Inspection · BLDG-QC | Dec 16, 2025 | Dec 16, 2025 | Approved |
Zoning review Planning · CP-ZOC | Dec 18, 2025 | Dec 18, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 12, 2026 | Jan 12, 2026 | Approved |
Zoning review Planning · CP-ZOC | Feb 11, 2026 | Feb 20, 2026 | Approved |
Building plan review Building Inspection · BLDG | Feb 11, 2026 | Mar 4, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Feb 11, 2026 | Feb 19, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 11, 2026 | Feb 25, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | Feb 11, 2026 | Feb 23, 2026 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Feb 11, 2026 | Mar 3, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 11, 2026 | Feb 18, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Feb 11, 2026 | Feb 28, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 11, 2026 | Feb 18, 2026 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Mar 3, 2026 | Mar 3, 2026 | Approved |
Zoning review Planning · CP-ZOC | Jun 18, 2026 | Jun 24, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jun 18, 2026 | Jul 15, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jun 18, 2026 | Jun 23, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 18, 2026 | Jul 7, 2026 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Jun 18, 2026 | Jun 22, 2026 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Jun 18, 2026 | Jun 29, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 18, 2026 | Jul 2, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jun 18, 2026 | Jul 2, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 18, 2026 | Jun 23, 2026 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Jul 1, 2026 | Aug 1, 2026 | Approved-Stipulated |
Zoning review Planning · CP-ZOC | Jul 28, 2026 | Jul 28, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jul 28, 2026 | Aug 3, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jul 28, 2026 | Jul 29, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 28, 2026 | Aug 3, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | Jul 28, 2026 | Jul 30, 2026 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Jul 28, 2026 | Aug 3, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 28, 2026 | Jul 30, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jul 28, 2026 | Aug 14, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 28, 2026 | Jul 30, 2026 | Approved |
Zoning review Planning · CP-ZOC | Jul 29, 2026 | Jul 30, 2026 | Approved |
CON CON-BOND | Aug 5, 2026 | Aug 5, 2026 | Approved |
Development fee collection Building Inspection · DFCU | Aug 13, 2026 | Aug 26, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Aug 27, 2026 | In progress | In Progress |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Approved
- Estimated cost
- $9,300,000
| Name | Role | License on permit |
|---|---|---|
| Lawrence Edward Schadt Gelfand Partners Architects | Architect | C29266 |
| David Owen Crestfield Triangle Engineering | Engineer | C050629 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025