54 Sussex St
San Francisco permit 202509044597 · Glen Park
New two story horizontal addition at rear yard, new media room and bathroom at basement level, new second story vertical addition: primary bedroom and bathroom, new exterior finishes at existing front facade, new main entry front door system at existing location, new interior renovations
- Filed
- Sep 22, 2025
- Issued
- Aug 14, 2026 (11 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 38 stops across 6 departments
- Comments issued
- 10 times, by Building Inspection, Public Works, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Sep 2, 2025 | Sep 15, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 17, 2025 | Sep 22, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Sep 22, 2025 | Nov 3, 2025 | Approved |
Building plan review Building Inspection · BLDG | Sep 22, 2025 | Oct 29, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Sep 22, 2025 | Oct 29, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 22, 2025 | Oct 22, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 22, 2025 | Oct 9, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 22, 2025 | Sep 25, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Sep 22, 2025 | Oct 24, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 22, 2025 | Sep 30, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Sep 22, 2025 | May 22, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jan 20, 2026 | Feb 2, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 20, 2026 | Jan 26, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 20, 2026 | Jan 27, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 20, 2026 | Jan 28, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jan 20, 2026 | Jan 21, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 20, 2026 | Jan 26, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jan 20, 2026 | Jan 28, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 20, 2026 | Jan 22, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jan 21, 2026 | Jan 21, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Mar 25, 2026 | Apr 6, 2026 | Approved |
Building plan review Building Inspection · BLDG | Mar 25, 2026 | Mar 30, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Mar 25, 2026 | Mar 30, 2026 | Not Applicable |
Mechanical and energy plan review Building Inspection · MECH | Mar 25, 2026 | Apr 1, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Mar 25, 2026 | Mar 31, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 25, 2026 | Mar 30, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Mar 25, 2026 | Apr 23, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 25, 2026 | Mar 27, 2026 | Approved |
Zoning review Planning · CP-ZOC | Apr 24, 2026 | May 7, 2026 | Approved |
Building plan review Building Inspection · BLDG | Apr 24, 2026 | May 13, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 24, 2026 | May 6, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Apr 24, 2026 | Apr 28, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 24, 2026 | Apr 27, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Apr 24, 2026 | May 20, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 24, 2026 | Apr 29, 2026 | Approved |
Fire prevention review Fire Department · SFFD | May 20, 2026 | May 20, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | May 22, 2026 | Aug 14, 2026 | Administrative |
Development fee collection Building Inspection · DFCU | May 26, 2026 | Jun 4, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $750,000
| Name | Role | License on permit |
|---|---|---|
| Patric Darren Mcmurtrie Mcm Architecture | Architect | C29072 |
| Jason Allen Pisano Hom Pisano | Engineer | C69708 |
| Benjamin Pan-Hon Lai Benjamin Lai & Associates | Engineer | 3268 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025