1800 Owens St
San Francisco permit 202509054634 · Potrero Hill
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Deferred submittal to pa# 202406255203 for frp structural only.
- Filed
- Sep 12, 2025
- Issued
- Jan 14, 2026 (4 months after filing)
- Completed
- Not completed yet
- Review stops
- 8 stops across 3 departments
- Comments issued
- Once, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Aug 29, 2025 | Sep 11, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 5, 2025 | Sep 16, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Sep 16, 2025 | Oct 22, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Sep 16, 2025 | Oct 16, 2025 | Not Applicable |
Fire prevention review Fire Department · SFFD | Sep 16, 2025 | Dec 9, 2025 | Not Applicable |
Permit Processing Center Building Inspection · PPC | Sep 16, 2025 | Dec 9, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Dec 4, 2025 | Dec 5, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 9, 2025 | Jan 14, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $1
| Name | Role | License on permit |
|---|---|---|
| Randall Robert Dowler Dowler Gruman Architects | Engineer | C23107 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026