2625 Balboa St
San Francisco permit 202509115082 · Outer Richmond
Relocating kitchen, replace 1/2 bath w/ full bath on 1/f. add windows at the rear pop-out of the building to match existing, adding new windows to the east facade at the 1st floor, and renovating the 2nd floor bathroom. repairs to the rear exterior facade will be undertaken where appropriate.
- Filed
- Sep 25, 2025
- Issued
- Feb 27, 2026 (5 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 31 stops across 5 departments
- Comments issued
- 7 times, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Sep 9, 2025 | Sep 22, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 23, 2025 | Sep 25, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Sep 25, 2025 | Sep 25, 2025 | Approved |
Building plan review Building Inspection · BLDG | Sep 25, 2025 | Oct 31, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Sep 25, 2025 | Oct 31, 2025 | Not Applicable |
Mechanical and energy plan review Building Inspection · MECH | Sep 25, 2025 | Oct 22, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 25, 2025 | Sep 26, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 25, 2025 | Sep 30, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Sep 25, 2025 | Feb 6, 2026 | Administrative |
Fire prevention review Fire Department · SFFD | Nov 7, 2025 | Nov 7, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Nov 10, 2025 | Nov 10, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 12, 2025 | Nov 12, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 18, 2025 | Nov 18, 2025 | Approved |
Building plan review Building Inspection · BLDG | Nov 21, 2025 | Nov 21, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Dec 12, 2025 | Dec 12, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 12, 2025 | Dec 12, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Dec 17, 2025 | Dec 17, 2025 | Approved-Stipulated |
Building plan review Building Inspection · BLDG | Dec 18, 2025 | Dec 18, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 30, 2025 | Dec 30, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jan 13, 2026 | Jan 13, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 13, 2026 | Jan 13, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 13, 2026 | Jan 14, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 13, 2026 | Jan 15, 2026 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Jan 23, 2026 | Jan 23, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Feb 4, 2026 | Feb 4, 2026 | Approved |
Building plan review Building Inspection · BLDG | Feb 4, 2026 | Feb 4, 2026 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Feb 4, 2026 | Feb 4, 2026 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Feb 4, 2026 | Feb 6, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Feb 4, 2026 | Feb 5, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 4, 2026 | Feb 6, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 6, 2026 | Feb 27, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $169,000
| Name | Role | License on permit |
|---|---|---|
| David L K Hayes Dh . Ad | Architect | C-37960 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2022