3217 Baker St
San Francisco permit 202509115083 · Marina
Horizontal addition to barhroom on 3/f.replace window in kind at front facade. enclose (e) lightwell. new hallway & renovation of (e) family room on 1/f. renovation of (e) kitchen & bathrooms on 2/f.
- Filed
- Oct 1, 2025
- Issued
- Feb 27, 2026 (5 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 35 stops across 6 departments
- Comments issued
- 9 times, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Sep 11, 2025 | Sep 11, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Sep 11, 2025 | Sep 11, 2025 | Approved |
Building plan review Building Inspection · BLDG | Sep 12, 2025 | Sep 12, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Sep 12, 2025 | Sep 12, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 12, 2025 | Sep 12, 2025 | Not Applicable |
Permit Center Permit Center · PERMIT-CTR | Sep 12, 2025 | Sep 29, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 29, 2025 | Oct 2, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Oct 2, 2025 | Oct 21, 2025 | Approved |
Building plan review Building Inspection · BLDG | Oct 2, 2025 | Nov 19, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Oct 2, 2025 | Nov 10, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 2, 2025 | Nov 7, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 2, 2025 | Oct 14, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Oct 2, 2025 | Oct 2, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Oct 2, 2025 | Feb 26, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Dec 12, 2025 | Dec 12, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 16, 2025 | Dec 16, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jan 7, 2026 | Jan 9, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 13, 2026 | Jan 13, 2026 | Approved |
Building plan review Building Inspection · BLDG | Feb 3, 2026 | Feb 6, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 3, 2026 | Feb 3, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Feb 4, 2026 | Feb 4, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Feb 4, 2026 | Feb 4, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 5, 2026 | Feb 9, 2026 | Approved |
Zoning review Planning · CP-ZOC | Feb 9, 2026 | Feb 9, 2026 | Approved |
Building plan review Building Inspection · BLDG | Feb 9, 2026 | Feb 18, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 9, 2026 | Feb 10, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 9, 2026 | Feb 12, 2026 | Approved |
Zoning review Planning · CP-ZOC | Feb 18, 2026 | Feb 18, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Feb 18, 2026 | Feb 18, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 18, 2026 | Feb 24, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Feb 18, 2026 | Feb 23, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Feb 18, 2026 | Feb 19, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 18, 2026 | Feb 20, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Feb 25, 2026 | Feb 25, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 26, 2026 | Feb 27, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $250,655
| Name | Role | License on permit |
|---|---|---|
| Aleck L Wilson Aleck Wilson Architects Inc | Architect | C25942 |
| Jason R Powers Zfa Structural Engineers | Engineer | 76130 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025