1339 11th Av
San Francisco permit 202509125204 · Inner Sunset
New 2-story horizontal addition @ rear yard, condition (e) unconditioned space @ 1/f, enlarge (e) garage door, remove (e) entry stairs, (n) entry 1/f, remodel/level (e) foundation & slab, (n) interior stairway/(n) sprial stair, (n) windows/doors/skylights (n)decks @ rear yard, (n)hvac/elec/plumbing
- Filed
- Sep 30, 2025
- Issued
- Mar 16, 2026 (5 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 31 stops across 6 departments
- Comments issued
- 12 times, by Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Sep 11, 2025 | Sep 26, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 29, 2025 | Oct 2, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Oct 2, 2025 | Oct 7, 2025 | Approved |
Building plan review Building Inspection · BLDG | Oct 2, 2025 | Nov 19, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Oct 2, 2025 | Nov 5, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 2, 2025 | Nov 7, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 2, 2025 | Oct 6, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Oct 2, 2025 | Oct 2, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Oct 2, 2025 | Oct 10, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Oct 2, 2025 | Oct 16, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Oct 2, 2025 | Mar 12, 2026 | Administrative |
Building plan review quality control Building Inspection · BLDG-QC | Nov 19, 2025 | Nov 19, 2025 | Approved |
Zoning review Planning · CP-ZOC | Dec 22, 2025 | Dec 31, 2025 | Approved |
Building plan review Building Inspection · BLDG | Dec 22, 2025 | Dec 29, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Dec 22, 2025 | Dec 30, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 22, 2025 | Dec 31, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 22, 2025 | Jan 5, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 22, 2025 | Dec 23, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Dec 22, 2025 | Jan 5, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Dec 22, 2025 | Dec 26, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jan 16, 2026 | Jan 21, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 16, 2026 | Jan 28, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jan 16, 2026 | Jan 20, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 16, 2026 | Jan 20, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jan 16, 2026 | Jan 29, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 16, 2026 | Jan 21, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jan 16, 2026 | Feb 9, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 16, 2026 | Jan 20, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jan 29, 2026 | Jan 29, 2026 | Administrative |
Urban forestry Public Works · DPW-BUF | Mar 12, 2026 | Mar 12, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 12, 2026 | Mar 16, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $210,896
| Name | Role | License on permit |
|---|---|---|
| Paul Chan Pctc Engineering | Engineer | C59840 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Nov 2014