185 Berry St
San Francisco permit 202509165412 · Mission Bay
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Revision to pa 202503263103 additition of a restaurant bar with associated revisions to the food service layout, equipment, & mep systems. exterior work has been modified to replace fixed steel trellises with retractable awnings. does not encroach public right of way.
- Filed
- Nov 6, 2025
- Issued
- Mar 12, 2026 (4 months after filing)
- Completed
- Not completed yet
- Review stops
- 36 stops across 6 departments
- Comments issued
- 13 times, by Building Inspection, Fire Department, Public Health
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Sep 16, 2025 | Sep 16, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Sep 26, 2025 | Sep 26, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 26, 2025 | Sep 26, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Sep 26, 2025 | Sep 26, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 29, 2025 | Sep 29, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Sep 30, 2025 | Sep 30, 2025 | Not Applicable |
Structural plan approval Building Inspection · PAD-STR | Oct 8, 2025 | Oct 8, 2025 | Approved |
Building plan review Building Inspection · BLDG | Oct 20, 2025 | Oct 20, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Oct 22, 2025 | Oct 22, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Oct 23, 2025 | Nov 4, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 24, 2025 | Nov 6, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Nov 6, 2025 | Dec 10, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 6, 2025 | Nov 26, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Nov 6, 2025 | Nov 13, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Nov 6, 2025 | Nov 18, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Nov 6, 2025 | Nov 10, 2025 | Approved |
Public Utilities programs review Public Utilities · SFPUC-PRG | Nov 6, 2025 | Nov 24, 2025 | Approved |
Public health food review Public Health · HEALTH-FD | Nov 6, 2025 | Nov 18, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Nov 6, 2025 | Mar 10, 2026 | Administrative |
Public health food review Public Health · HEALTH-FD | Dec 5, 2025 | Dec 5, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 10, 2025 | Dec 10, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jan 28, 2026 | Feb 2, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 25, 2026 | Feb 27, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Feb 25, 2026 | Mar 9, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 25, 2026 | Mar 2, 2026 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Feb 25, 2026 | Feb 27, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 25, 2026 | Feb 27, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Feb 25, 2026 | Feb 26, 2026 | Approved |
Public Utilities programs review Public Utilities · SFPUC-PRG | Feb 25, 2026 | Feb 26, 2026 | Approved |
Public health food review Public Health · HEALTH-FD | Feb 25, 2026 | Mar 6, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | Mar 3, 2026 | Mar 3, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 5, 2026 | Mar 5, 2026 | Approved |
Building plan review Building Inspection · BLDG | Mar 6, 2026 | Mar 6, 2026 | Administrative |
Public health food review Public Health · HEALTH-FD | Mar 6, 2026 | Mar 6, 2026 | Administrative |
Fire prevention review Fire Department · SFFD | Mar 9, 2026 | Mar 9, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 10, 2026 | Mar 12, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $250,000
| Name | Role | License on permit |
|---|---|---|
| Cass Calder Smith Ccs Architecture | Architect | C22469 |
| Michael Paul Gemmill Nabih Youssef Associats | Engineer | 4703 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026