1407 Dolores St
San Francisco permit 202509175527 · Noe Valley
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Revision to permit 202508183269. interior remodel to (e) dwelling units on 2/f and 3/f including 2 (e) kitchens and bathroom and add 1 new bathroom per unit (2 total). add roof deck a top 2nd floor projection. rebuild rear stair in revised configuration. replace all windows and doors on 2nd and 3rd
- Filed
- Oct 27, 2025
- Issued
- Apr 13, 2026 (6 months after filing)
- Completed
- Not completed yet
- Review stops
- 36 stops across 5 departments
- Comments issued
- 5 times, by Public Utilities, Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Sep 17, 2025 | Sep 17, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Sep 17, 2025 | Sep 17, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Sep 17, 2025 | Sep 17, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 17, 2025 | Sep 17, 2025 | Issued Comments |
Intake Building Inspection · INTAKE | Oct 1, 2025 | Oct 1, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Oct 1, 2025 | Oct 1, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 7, 2025 | Oct 7, 2025 | Approved |
Permit Center Permit Center · PERMIT-CTR | Oct 12, 2025 | Oct 24, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 24, 2025 | Oct 28, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Oct 28, 2025 | Jan 21, 2026 | Approved |
Building plan review Building Inspection · BLDG | Oct 28, 2025 | Dec 5, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Oct 28, 2025 | Dec 5, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 28, 2025 | Nov 20, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Oct 28, 2025 | Oct 30, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Oct 28, 2025 | Oct 29, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Oct 28, 2025 | Mar 16, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Jan 15, 2026 | Jan 28, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jan 15, 2026 | Jan 28, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 15, 2026 | Jan 23, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jan 15, 2026 | Jan 21, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 15, 2026 | Jan 16, 2026 | Approved |
Zoning review Planning · CP-ZOC | Feb 12, 2026 | Feb 24, 2026 | Approved |
Building plan review Building Inspection · BLDG | Feb 12, 2026 | Feb 27, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Feb 12, 2026 | Feb 27, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 12, 2026 | Feb 17, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Feb 12, 2026 | Feb 18, 2026 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Feb 12, 2026 | Feb 17, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Feb 18, 2026 | Feb 18, 2026 | Approved |
Zoning review Planning · CP-ZOC | Mar 2, 2026 | Mar 2, 2026 | Approved |
Building plan review Building Inspection · BLDG | Mar 2, 2026 | Mar 9, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Mar 2, 2026 | Mar 9, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 2, 2026 | Mar 2, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Mar 2, 2026 | Mar 16, 2026 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Mar 2, 2026 | Mar 3, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Mar 16, 2026 | Mar 16, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 16, 2026 | Apr 13, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $280,000
| Name | Role | License on permit |
|---|---|---|
| Gary Wayne Meyer Wayne Myer Works Arch | Architect | C31705 |
| Michael Austin Hom Hom Pisano Engineering Inc. | Engineer | C71450 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2025