1511 Haight St
San Francisco permit 202509175545 · Haight Ashbury
Renovation of an existing music venue out of operation for several years. owners proposing barrier remediation with enlarged restroom, new finishes, and lighting throughout public area. new sound baffling to replace existing, reuse existing storerront doors. replace non functional power door operato
- Filed
- Sep 17, 2025
- Issued
- Nov 17, 2025 (2 months after filing)
- Completed
- Jun 15, 2026 (7 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2025 were typically issued within 1 month (median of 5,178 issued permits).
- Review stops
- 19 stops across 5 departments
- Comments issued
- 6 times, by Planning, Building Inspection, Public Works, Public Health
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Apartment and hotel inspection Building Inspection · HIS | Sep 17, 2025 | Sep 17, 2025 | Administrative |
Intake Building Inspection · INTAKE | Sep 17, 2025 | Sep 17, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Sep 17, 2025 | Sep 17, 2025 | Issued Comments |
Intake Building Inspection · INTAKE | Oct 2, 2025 | Oct 2, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Oct 3, 2025 | Oct 3, 2025 | Approved |
Zoning review Planning · CP-ZOC | Oct 6, 2025 | Oct 6, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Oct 15, 2025 | Oct 15, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Oct 15, 2025 | Oct 15, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Oct 15, 2025 | Oct 15, 2025 | Issued Comments |
Public health review Public Health · HEALTH | Oct 15, 2025 | Oct 15, 2025 | Administrative |
Public health food review Public Health · HEALTH-FD | Oct 15, 2025 | Oct 15, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Oct 27, 2025 | Oct 27, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Oct 29, 2025 | Oct 29, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 30, 2025 | Oct 30, 2025 | Approved |
Public health food review Public Health · HEALTH-FD | Oct 31, 2025 | Oct 31, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Nov 4, 2025 | Nov 4, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Nov 4, 2025 | Nov 4, 2025 | Approved |
Building plan review Building Inspection · BLDG | Nov 6, 2025 | Nov 6, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 12, 2025 | Nov 17, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $150,000
| Name | Role | License on permit |
|---|---|---|
| Steven B Hall Shc | Architect | C28168 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2022