1011 Turk St
San Francisco permit 202509225808 · Western Addition
Ups replacements including batteries with structural anchrage & removed of existing equipement. installation of nw transformer & removal of existing tranformer, removed of existing mechanical unit & intallation of new ac unit, cutting & patching of finshes, fire partitions & fire rate doors
- Filed
- Sep 22, 2025
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 10 stops across 3 departments
- Comments issued
- Twice, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Sep 22, 2025 | Sep 22, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Sep 22, 2025 | Sep 22, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 22, 2025 | Sep 22, 2025 | Issued Comments |
Public Works disability access review Public Works · PW-DAC | Sep 22, 2025 | Sep 22, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Sep 23, 2025 | Sep 23, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 23, 2025 | Sep 23, 2025 | Not Applicable |
Structural plan approval Building Inspection · PAD-STR | Oct 20, 2025 | Oct 20, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 20, 2025 | Oct 20, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Oct 21, 2025 | Oct 21, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Filed
- Estimated cost
- $1,195,498
| Name | Role | License on permit |
|---|---|---|
| Paul I Cooper Tef Design | Architect | C28490 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026