299 West Portal Av
San Francisco permit 202509235912 · West of Twin Peaks
Change of use tenant improvement & minor expansion (nw eleveation). (n) retail health services ophthalmology clinic & relocated retail & personal services. (n) office based surgical spaces shall operate under license of dr's & is not subject to review by hchi (oshpd) nor as an asc.
- Filed
- Nov 24, 2025
- Issued
- Aug 28, 2026 (9 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 43 stops across 7 departments
- Comments issued
- 7 times, by Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Sep 23, 2025 | Sep 23, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Sep 23, 2025 | Sep 23, 2025 | Approved |
Building plan review Building Inspection · BLDG | Sep 25, 2025 | Sep 25, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 25, 2025 | Sep 25, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Sep 26, 2025 | Sep 26, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 26, 2025 | Sep 26, 2025 | Not Applicable |
Street use and mapping Public Works · DPW-BSM | Sep 26, 2025 | Sep 26, 2025 | Approved |
Public health review Public Health · HEALTH | Sep 26, 2025 | Sep 26, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 1, 2025 | Oct 1, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Oct 6, 2025 | Oct 6, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 9, 2025 | Oct 9, 2025 | Approved |
Building plan review Building Inspection · BLDG | Oct 10, 2025 | Oct 10, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Oct 15, 2025 | Oct 15, 2025 | Approved |
Permit Center Permit Center · PERMIT-CTR | Oct 21, 2025 | Nov 5, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 23, 2025 | Nov 25, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Nov 25, 2025 | Nov 26, 2025 | Approved |
Building plan review Building Inspection · BLDG | Nov 25, 2025 | Dec 18, 2025 | Not Applicable |
Structural plan approval Building Inspection · PAD-STR | Nov 25, 2025 | Dec 26, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 25, 2025 | Dec 16, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Nov 25, 2025 | Dec 2, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Nov 25, 2025 | Nov 25, 2025 | Approved |
Public Health HEALTH-HM | Nov 25, 2025 | Nov 26, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Nov 25, 2025 | Apr 21, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Dec 30, 2025 | Jan 5, 2026 | Approved |
Building plan review Building Inspection · BLDG | Dec 30, 2025 | Jan 16, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Dec 30, 2025 | Jan 7, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 30, 2025 | Jan 5, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | Dec 30, 2025 | Dec 31, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 30, 2025 | Dec 31, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Dec 30, 2025 | Jan 6, 2026 | Approved |
Public Health HEALTH-HM | Dec 30, 2025 | Dec 31, 2025 | Approved |
Building plan review Building Inspection · BLDG | Dec 31, 2025 | Dec 31, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jan 13, 2026 | Jan 13, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 16, 2026 | Jan 16, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 16, 2026 | Jan 16, 2026 | Approved |
Development fee collection Building Inspection · DFCU | Jan 16, 2026 | Jan 16, 2026 | Administrative |
Electrical plan review Building Inspection · MECH-E | Jan 20, 2026 | Jan 20, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 20, 2026 | Jan 20, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 16, 2026 | Apr 17, 2026 | Approved |
Zoning review Planning · CP-ZOC | Apr 17, 2026 | Apr 20, 2026 | Approved |
Public Health HEALTH-HM | Apr 17, 2026 | Apr 21, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 21, 2026 | Aug 28, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Aug 25, 2026 | Aug 25, 2026 | Approved |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $1,108,500
| Name | Role | License on permit |
|---|---|---|
| John Git Hoong Lum John Lum Architecture | Architect | 21837 |
| Vahid Sattary Sattart Structural Engineer | Engineer | 3973 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025