Scope of work
As written on the permit application.

Convert the ground floor (e) storage area located at the rear of the building to be an adu with 2 new bedrooms, 1 new bathroom & 1 new kitchen / dining space.

Timeline
Key dates from the city record.
Filed
Oct 22, 2025
Issued
Jun 29, 2026 (8 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
31 stops across 6 departments
Comments issued
6 times, by Building Inspection, Fire Department
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Oct 10, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Oct 23, 2025Administrative

Zoning review

Planning · CP-ZOC

Oct 28, 2025Approved

Building plan review

Building Inspection · BLDG

Oct 30, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Nov 3, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Oct 31, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

Oct 28, 2025Issued Comments

Street use and mapping

Public Works · DPW-BSM

Oct 28, 2025Approved

Urban forestry

Public Works · DPW-BUF

Nov 12, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Oct 31, 2025Approved

Permit Processing Center

Building Inspection · PPC

Feb 25, 2026Administrative

Zoning review

Planning · CP-ZOC

Jan 28, 2026Approved

Building plan review

Building Inspection · BLDG

Feb 4, 2026Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Feb 3, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

Jan 27, 2026Approved

Fire prevention review

Fire Department · SFFD

Jan 23, 2026Issued Comments

Street use and mapping

Public Works · DPW-BSM

Jan 26, 2026Approved

Urban forestry

Public Works · DPW-BUF

Feb 3, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jan 20, 2026Approved

Zoning review

Planning · CP-ZOC

Feb 19, 2026Approved

Building plan review

Building Inspection · BLDG

Feb 20, 2026Approved

Structural plan approval

Building Inspection · PAD-STR

Feb 18, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

Feb 18, 2026Approved

Fire prevention review

Fire Department · SFFD

Feb 13, 2026Approved-Stipulated

Street use and mapping

Public Works · DPW-BSM

Feb 11, 2026Approved

Urban forestry

Public Works · DPW-BUF

Feb 24, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

Feb 12, 2026Approved

Development fee collection

Building Inspection · DFCU

Feb 24, 2026Administrative

Building plan review quality control

Building Inspection · BLDG-QC

Feb 25, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Jun 29, 2026Administrative

Address verification

Building Inspection · ADDR

Jun 26, 2026Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$153,064
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Hongbo Yang

W.H. Consultant, Inc

EngineerC88467
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202509235946 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record