1251 19th Av
San Francisco permit 202509235946 · Sunset/Parkside
Convert the ground floor (e) storage area located at the rear of the building to be an adu with 2 new bedrooms, 1 new bathroom & 1 new kitchen / dining space.
- Filed
- Oct 22, 2025
- Issued
- Jun 29, 2026 (8 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 31 stops across 6 departments
- Comments issued
- 6 times, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Sep 22, 2025 | Oct 10, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 24, 2025 | Oct 23, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Oct 23, 2025 | Oct 28, 2025 | Approved |
Building plan review Building Inspection · BLDG | Oct 23, 2025 | Oct 30, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Oct 23, 2025 | Nov 3, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 23, 2025 | Oct 31, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 23, 2025 | Oct 28, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Oct 23, 2025 | Oct 28, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Oct 23, 2025 | Nov 12, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 23, 2025 | Oct 31, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Oct 23, 2025 | Feb 25, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jan 20, 2026 | Jan 28, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 20, 2026 | Feb 4, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 20, 2026 | Feb 3, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 20, 2026 | Jan 27, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jan 20, 2026 | Jan 23, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jan 20, 2026 | Jan 26, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jan 20, 2026 | Feb 3, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 20, 2026 | Jan 20, 2026 | Approved |
Zoning review Planning · CP-ZOC | Feb 10, 2026 | Feb 19, 2026 | Approved |
Building plan review Building Inspection · BLDG | Feb 10, 2026 | Feb 20, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Feb 10, 2026 | Feb 18, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 10, 2026 | Feb 18, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Feb 10, 2026 | Feb 13, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Feb 10, 2026 | Feb 11, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Feb 10, 2026 | Feb 24, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 10, 2026 | Feb 12, 2026 | Approved |
Development fee collection Building Inspection · DFCU | Feb 24, 2026 | Feb 24, 2026 | Administrative |
Building plan review quality control Building Inspection · BLDG-QC | Feb 25, 2026 | Feb 25, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 25, 2026 | Jun 29, 2026 | Administrative |
Address verification Building Inspection · ADDR | Jun 26, 2026 | Jun 26, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $153,064
| Name | Role | License on permit |
|---|---|---|
| Hongbo Yang W.H. Consultant, Inc | Engineer | C88467 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2024