As written on the permit application.

Change of occupancy and use of space from office (b) to karaoke lounge (a-2). minor demo of plumbing fixtures, millwork, rehanging restroom doors. no food service.

Timeline
Key dates from the city record.
Filed
Apr 27, 2026
Issued
Sep 16, 2026 (5 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
27 stops across 6 departments
Comments issued
5 times, by Planning, Building Inspection, Fire Department, Public Health
Review stopFinishedResult

Intake

Building Inspection · INTAKE

Sep 23, 2025Administrative

Zoning review

Planning · CP-ZOC

Sep 23, 2025Issued Comments

Zoning review

Planning · CP-ZOC

Oct 6, 2025Issued Comments

Zoning review

Planning · CP-ZOC

Oct 8, 2025Approved

Intake

Building Inspection · INTAKE

Feb 20, 2026Administrative

Zoning review

Planning · CP-ZOC

Feb 20, 2026Approved

Intake

Building Inspection · INTAKE

Mar 31, 2026Administrative

Zoning review

Planning · CP-ZOC

Mar 31, 2026Approved

Building plan review

Building Inspection · BLDG

Mar 31, 2026Issued Comments

Intake

Building Inspection · INTAKE

Apr 8, 2026Administrative

Zoning review

Planning · CP-ZOC

Apr 8, 2026Approved

Building plan review

Building Inspection · BLDG

Apr 13, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

Apr 13, 2026Approved-Stipulated

Fire prevention review

Fire Department · SFFD

Apr 13, 2026Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Apr 13, 2026Approved

Permit Center

Permit Center · PERMIT-CTR

Apr 24, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Apr 30, 2026Administrative

Zoning review

Planning · CP-ZOC

May 4, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

Jun 5, 2026Approved-Stipulated

Fire prevention review

Fire Department · SFFD

Jul 28, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

May 4, 2026Approved

Public health review

Public Health · HEALTH

Apr 30, 2026Administrative

Public health food review

Public Health · HEALTH-FD

May 21, 2026Issued Comments

Permit Processing Center

Building Inspection · PPC

Sep 2, 2026Administrative

Public health food review

Public Health · HEALTH-FD

Aug 26, 2026Not Applicable

Central Permit Bureau

Building Inspection · CPB

Sep 16, 2026Administrative

Development fee collection

Building Inspection · DFCU

Sep 3, 2026Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$4,500
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Brian T Milford

Martinkovic Milford Architects

ArchitectC33430
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202509235962 on the city's permit tracking site