2722 Irving St
San Francisco permit 202509266160 · Sunset/Parkside
Proposed to convert basement space into a 468 sf jadu, the jadu will consist of a kitchenette, entertainment area, bedroom, one bathroom, and a laundry area. the existing single-family house main floor and second floor are not included in the scope of work.
- Filed
- Dec 1, 2025
- Issued
- Jun 10, 2026 (6 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 46 stops across 6 departments
- Comments issued
- 10 times, by Planning, Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Sep 22, 2025 | Oct 7, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 8, 2025 | Dec 2, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Dec 2, 2025 | Dec 11, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 2, 2025 | Dec 19, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Dec 2, 2025 | Dec 18, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 2, 2025 | Dec 17, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 2, 2025 | Dec 5, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Dec 2, 2025 | Dec 3, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Dec 2, 2025 | Dec 29, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Dec 2, 2025 | Dec 23, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Dec 2, 2025 | May 18, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Feb 12, 2026 | Feb 18, 2026 | Approved |
Building plan review Building Inspection · BLDG | Feb 12, 2026 | Feb 24, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Feb 12, 2026 | Mar 4, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 12, 2026 | Feb 12, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Feb 12, 2026 | Feb 20, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 12, 2026 | Feb 18, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Feb 12, 2026 | Feb 28, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 12, 2026 | Feb 17, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Feb 20, 2026 | Feb 20, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Mar 9, 2026 | Mar 9, 2026 | Approved |
Building plan review Building Inspection · BLDG | Mar 9, 2026 | Mar 12, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Mar 9, 2026 | Mar 30, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 9, 2026 | Mar 9, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Mar 9, 2026 | Mar 11, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 9, 2026 | Mar 11, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Mar 9, 2026 | Mar 19, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 9, 2026 | Mar 9, 2026 | Approved |
Zoning review Planning · CP-ZOC | Apr 1, 2026 | Apr 1, 2026 | Approved |
Building plan review Building Inspection · BLDG | Apr 1, 2026 | Apr 10, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Apr 1, 2026 | Apr 9, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 1, 2026 | Apr 2, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Apr 1, 2026 | Apr 8, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 1, 2026 | Apr 8, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Apr 1, 2026 | May 5, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 1, 2026 | Apr 3, 2026 | Approved |
Zoning review Planning · CP-ZOC | Apr 29, 2026 | May 13, 2026 | Approved |
Building plan review Building Inspection · BLDG | Apr 29, 2026 | May 12, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Apr 29, 2026 | May 5, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 29, 2026 | May 5, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Apr 29, 2026 | May 1, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 29, 2026 | May 4, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 29, 2026 | May 1, 2026 | Approved |
Development fee collection Building Inspection · DFCU | May 13, 2026 | May 13, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | May 18, 2026 | Jun 10, 2026 | Administrative |
Address verification Building Inspection · ADDR | May 27, 2026 | May 27, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $242,943
| Name | Role | License on permit |
|---|---|---|
| Sujin Sung Sujin Sung Engineering | Engineer | C78186 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2025