1089 03rd St
San Francisco permit 202509266165 · Mission Bay
Proj#25-0621-mou port: alteration to existing floor plates on level 6,7,& 8.demo existing slab & create floor openings as shown, for future tenant improvements.provide temporary code compliance with smoke control report.
- Filed
- Oct 10, 2025
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 18 stops across 3 departments
- Comments issued
- 7 times, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Sep 23, 2025 | Oct 1, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 1, 2025 | Oct 10, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Oct 10, 2025 | Nov 7, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Oct 10, 2025 | Oct 31, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 10, 2025 | Oct 23, 2025 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Oct 10, 2025 | Oct 17, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Oct 10, 2025 | Dec 22, 2025 | Administrative |
Fire Department SFFD-PRT | Oct 16, 2025 | Oct 17, 2025 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Oct 20, 2025 | Oct 20, 2025 | Administrative |
Building plan review quality control Building Inspection · BLDG-QC | Nov 6, 2025 | Nov 6, 2025 | Approved |
Building plan review Building Inspection · BLDG | Nov 17, 2025 | Dec 1, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Nov 17, 2025 | Dec 15, 2025 | Approved |
Fire Department SFFD-PRT | Nov 17, 2025 | Nov 17, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 25, 2025 | Nov 25, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 12, 2025 | Dec 12, 2025 | Approved |
Fire Department SFFD-PRT | Dec 12, 2025 | Dec 16, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 17, 2025 | Dec 17, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 22, 2025 | Jan 13, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Approved
- Estimated cost
- $1,750,000
| Name | Role | License on permit |
|---|---|---|
| Marc Pfenninger Studios Architecture | Architect | C27880 |
| Mark Thomas Koenigs Thornton Tomasetti | Engineer | S6051 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026