348 Cumberland St
San Francisco permit 202509266168 · Castro/Upper Market
Conversion of 356 sf of (e) garage to living area. reconfiguration of (e) interior stair between first and second fls. remodel of (e) 2nd fl kitchen & bath.
- Filed
- Oct 27, 2025
- Issued
- Jan 12, 2026 (3 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 20 stops across 5 departments
- Comments issued
- 3 times, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Sep 26, 2025 | Sep 26, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Sep 26, 2025 | Sep 26, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 26, 2025 | Sep 26, 2025 | Approved |
Permit Center Permit Center · PERMIT-CTR | Sep 26, 2025 | Oct 9, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 10, 2025 | Oct 28, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Oct 28, 2025 | Oct 29, 2025 | Approved |
Building plan review Building Inspection · BLDG | Oct 28, 2025 | Dec 9, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Oct 28, 2025 | Dec 5, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 28, 2025 | Nov 21, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Oct 28, 2025 | Oct 30, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Oct 28, 2025 | Nov 13, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Oct 28, 2025 | Jan 5, 2026 | Administrative |
Building plan review quality control Building Inspection · BLDG-QC | Dec 8, 2025 | Dec 8, 2025 | Approved |
Zoning review Planning · CP-ZOC | Dec 11, 2025 | Dec 15, 2025 | Approved |
Building plan review Building Inspection · BLDG | Dec 11, 2025 | Dec 23, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Dec 11, 2025 | Dec 18, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 11, 2025 | Dec 30, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Dec 11, 2025 | Dec 23, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 11, 2025 | Dec 18, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 5, 2026 | Jan 12, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $286,567
| Name | Role | License on permit |
|---|---|---|
| Roberta A Wahl Plum Architects | Architect | C28322 |
| Albert Urrutia Atrium Structural Engineer | Engineer | S2994 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Aug 2016