323 Staples Av
San Francisco permit 202509306377 · West of Twin Peaks
Legalization of adu. 2-story horizontal addition. remodel of both 1st & 2nd floors including removal of unauthorized storage at rear of building.
- Filed
- Oct 15, 2025
- Issued
- May 8, 2026 (7 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 32 stops across 6 departments
- Comments issued
- 7 times, by Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Sep 29, 2025 | Oct 10, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 15, 2025 | Oct 15, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Oct 16, 2025 | Oct 16, 2025 | Approved |
Building plan review Building Inspection · BLDG | Oct 16, 2025 | Nov 13, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Oct 16, 2025 | Nov 5, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 16, 2025 | Oct 29, 2025 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Oct 16, 2025 | Oct 20, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Oct 16, 2025 | Oct 20, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Oct 16, 2025 | Nov 14, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Oct 16, 2025 | Oct 24, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Oct 16, 2025 | Apr 21, 2026 | Administrative |
Building plan review quality control Building Inspection · BLDG-QC | Nov 6, 2025 | Nov 10, 2025 | Approved |
Zoning review Planning · CP-ZOC | Feb 10, 2026 | Feb 11, 2026 | Approved |
Building plan review Building Inspection · BLDG | Feb 10, 2026 | Mar 10, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Feb 10, 2026 | Feb 18, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 10, 2026 | Feb 19, 2026 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Feb 10, 2026 | Feb 17, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Feb 10, 2026 | Feb 11, 2026 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Feb 10, 2026 | Mar 10, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 10, 2026 | Feb 18, 2026 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Feb 23, 2026 | Feb 23, 2026 | Approved |
Zoning review Planning · CP-ZOC | Mar 19, 2026 | Mar 23, 2026 | Approved |
Building plan review Building Inspection · BLDG | Mar 19, 2026 | Mar 23, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Mar 19, 2026 | Mar 31, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 19, 2026 | Apr 9, 2026 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Mar 19, 2026 | Mar 21, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Mar 19, 2026 | Apr 1, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Mar 19, 2026 | Apr 21, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 19, 2026 | Mar 20, 2026 | Approved |
Development fee collection Building Inspection · DFCU | Apr 21, 2026 | Apr 21, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Apr 21, 2026 | May 8, 2026 | Administrative |
Address verification Building Inspection · ADDR | Apr 27, 2026 | Apr 27, 2026 | Approved |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $340,806
| Name | Role | License on permit |
|---|---|---|
| Avetik Eloyan Eloyan Architect | Architect | C36084 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2011