CheckMyDesigner

323 Staples Av

San Francisco permit 202509306377 · West of Twin Peaks

ADUFull plan reviewIssued
Street view · Apr 2011
Google Street View of 323 Staples Av, Apr 2011
Scope of work
As written on the permit application.

Legalization of adu. 2-story horizontal addition. remodel of both 1st & 2nd floors including removal of unauthorized storage at rear of building.

Timeline
Key dates from the city record.
Filed
Oct 15, 2025
Issued
May 8, 2026 (7 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
32 stops across 6 departments
Comments issued
7 times, by Building Inspection, Fire Department, Public Works
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Oct 10, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Oct 15, 2025Administrative

Zoning review

Planning · CP-ZOC

Oct 16, 2025Approved

Building plan review

Building Inspection · BLDG

Nov 13, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Nov 5, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Oct 29, 2025Issued Comments

Fire Department housing review

Fire Department · SFFD-HQ

Oct 20, 2025Issued Comments

Street use and mapping

Public Works · DPW-BSM

Oct 20, 2025Approved

Urban forestry

Public Works · DPW-BUF

Nov 14, 2025Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Oct 24, 2025Approved

Permit Processing Center

Building Inspection · PPC

Apr 21, 2026Administrative

Building plan review quality control

Building Inspection · BLDG-QC

Nov 10, 2025Approved

Zoning review

Planning · CP-ZOC

Feb 11, 2026Approved

Building plan review

Building Inspection · BLDG

Mar 10, 2026Approved

Structural plan approval

Building Inspection · PAD-STR

Feb 18, 2026Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Feb 19, 2026Approved

Fire Department housing review

Fire Department · SFFD-HQ

Feb 17, 2026Approved-Stipulated

Street use and mapping

Public Works · DPW-BSM

Feb 11, 2026Issued Comments

Urban forestry

Public Works · DPW-BUF

Mar 10, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

Feb 18, 2026Approved

Building plan review quality control

Building Inspection · BLDG-QC

Feb 23, 2026Approved

Zoning review

Planning · CP-ZOC

Mar 23, 2026Approved

Building plan review

Building Inspection · BLDG

Mar 23, 2026Approved

Structural plan approval

Building Inspection · PAD-STR

Mar 31, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

Apr 9, 2026Approved

Fire Department housing review

Fire Department · SFFD-HQ

Mar 21, 2026Approved-Stipulated

Street use and mapping

Public Works · DPW-BSM

Apr 1, 2026Approved

Urban forestry

Public Works · DPW-BUF

Apr 21, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

Mar 20, 2026Approved

Development fee collection

Building Inspection · DFCU

Apr 21, 2026Administrative

Central Permit Bureau

Building Inspection · CPB

May 8, 2026Administrative

Address verification

Building Inspection · ADDR

Apr 27, 2026Approved

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$340,806
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Avetik Eloyan

Eloyan Architect

ArchitectC36084
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202509306377 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record