9 A 25th Ave North Av
San Francisco permit 202509306381 · Seacliff
New construction of adu: a 2-story type-v with fire sprinklers
- Filed
- Oct 16, 2025
- Issued
- Dec 19, 2025 (2 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 21 stops across 6 departments
- Comments issued
- 3 times, by Building Inspection, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Sep 26, 2025 | Oct 14, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 17, 2025 | Oct 17, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Oct 17, 2025 | Nov 5, 2025 | Approved |
Building plan review Building Inspection · BLDG | Oct 17, 2025 | Nov 6, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Oct 17, 2025 | Nov 6, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Oct 17, 2025 | Oct 31, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 17, 2025 | Oct 20, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 17, 2025 | Oct 20, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Oct 17, 2025 | Nov 15, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 17, 2025 | Nov 4, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Oct 17, 2025 | Dec 9, 2025 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | Nov 4, 2025 | Nov 4, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 14, 2025 | Nov 14, 2025 | Approved |
Zoning review Planning · CP-ZOC | Nov 20, 2025 | Nov 25, 2025 | Approved |
Building plan review Building Inspection · BLDG | Nov 20, 2025 | Nov 20, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Nov 20, 2025 | Nov 26, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 20, 2025 | Nov 24, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 20, 2025 | Nov 25, 2025 | Approved |
Development fee collection Building Inspection · DFCU | Dec 1, 2025 | Dec 5, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Dec 2, 2025 | Dec 2, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 9, 2025 | Dec 19, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Issued
- Estimated cost
- $170,730
| Name | Role | License on permit |
|---|---|---|
| Federico Engel Butler Armsden Architecture | Architect | C32207 |
| David M Strandberg Strandberg Engineering | Engineer | 62993 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025