214 Bonview St
San Francisco permit 202510026603 · Bernal Heights
Addition & renovation to main home w/ new bathroom and bedrooms added. renovation to apartment including partial renovation of kitchen & bathroom.
- Filed
- Oct 21, 2025
- Issued
- Apr 13, 2026 (6 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 23 stops across 6 departments
- Comments issued
- 8 times, by Building Inspection, Public Works, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Sep 30, 2025 | Oct 9, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 14, 2025 | Oct 22, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Oct 22, 2025 | Oct 23, 2025 | Approved |
Building plan review Building Inspection · BLDG | Oct 22, 2025 | Nov 25, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Oct 22, 2025 | Nov 25, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Oct 22, 2025 | Nov 6, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 22, 2025 | Oct 29, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 22, 2025 | Oct 28, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Oct 22, 2025 | Nov 20, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Oct 22, 2025 | Nov 7, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Oct 22, 2025 | Mar 27, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jan 21, 2026 | Jan 21, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 21, 2026 | Feb 3, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 21, 2026 | Jan 26, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jan 21, 2026 | Jan 27, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 21, 2026 | Jan 22, 2026 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Jan 21, 2026 | Feb 3, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 21, 2026 | Jan 22, 2026 | Issued Comments |
Zoning review Planning · CP-ZOC | Jan 23, 2026 | Jan 28, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 23, 2026 | Jan 29, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 23, 2026 | Jan 28, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 26, 2026 | Mar 26, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 27, 2026 | Apr 13, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $487,945
| Name | Role | License on permit |
|---|---|---|
| Patrick B Perez Designpad Architecture | Architect | C-30230 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2023