San Francisco permit 202510026610 · Russian Hill

Home remodelFull plan reviewIssued
Street view · Sep 2026
Google Street View of 1486 Jackson St #0, Sep 2026
Scope of work
As written on the permit application.

Unit 1486 - 2nd fl: demo all (e) construction back to framing, add bedroom, new kitchen, additional bathroom, all new mech system & structural upgrades. no bldg envelope changes, no sq ft added.

Timeline
Key dates from the city record.
Filed
Dec 16, 2025
Issued
Apr 9, 2026 (4 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
24 stops across 5 departments
Comments issued
8 times, by Building Inspection, Fire Department, Public Utilities
Review stopFinishedResult

Intake

Building Inspection · INTAKE

Oct 2, 2025Administrative

Zoning review

Planning · CP-ZOC

Oct 2, 2025Not Applicable

Permit Center

Permit Center · PERMIT-CTR

Dec 12, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Dec 16, 2025Administrative

Permit Processing Center

Building Inspection · PPC

Apr 3, 2026Administrative

Building plan review

Building Inspection · BLDG

Feb 6, 2026Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Jan 28, 2026Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jan 8, 2026Issued Comments

Fire prevention review

Fire Department · SFFD

Dec 22, 2025Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Dec 30, 2025Issued Comments

Building plan review quality control

Building Inspection · BLDG-QC

Feb 6, 2026Approved

Building plan review

Building Inspection · BLDG

Feb 9, 2026Issued Comments

Building plan review

Building Inspection · BLDG

Mar 6, 2026Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Mar 10, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

Mar 11, 2026Approved

Fire prevention review

Fire Department · SFFD

Mar 11, 2026Approved

Building plan review

Building Inspection · BLDG

Mar 13, 2026Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Mar 10, 2026Approved

Building plan review

Building Inspection · BLDG

Mar 24, 2026Approved

Structural plan approval

Building Inspection · PAD-STR

Mar 18, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

Mar 23, 2026Approved

Fire prevention review

Fire Department · SFFD

Apr 3, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

Mar 20, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Apr 9, 2026Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$347,771
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Andrew Ross Levine

Levine Architects

ArchitectC14090
Albert Urrutia

Atrium Structural Engineer

EngineerS2994
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202510026610 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record