1486 Jackson St #0
San Francisco permit 202510026610 · Russian Hill
Unit 1486 - 2nd fl: demo all (e) construction back to framing, add bedroom, new kitchen, additional bathroom, all new mech system & structural upgrades. no bldg envelope changes, no sq ft added.
- Filed
- Dec 16, 2025
- Issued
- Apr 9, 2026 (4 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 24 stops across 5 departments
- Comments issued
- 8 times, by Building Inspection, Fire Department, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Oct 2, 2025 | Oct 2, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Oct 2, 2025 | Oct 2, 2025 | Not Applicable |
Permit Center Permit Center · PERMIT-CTR | Nov 20, 2025 | Dec 12, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 12, 2025 | Dec 16, 2025 | Administrative |
Permit Processing Center Building Inspection · PPC | Dec 16, 2025 | Apr 3, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Dec 18, 2025 | Feb 6, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Dec 18, 2025 | Jan 28, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 18, 2025 | Jan 8, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 18, 2025 | Dec 22, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Dec 18, 2025 | Dec 30, 2025 | Issued Comments |
Building plan review quality control Building Inspection · BLDG-QC | Feb 6, 2026 | Feb 6, 2026 | Approved |
Building plan review Building Inspection · BLDG | Feb 9, 2026 | Feb 9, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 2, 2026 | Mar 6, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Mar 2, 2026 | Mar 10, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 2, 2026 | Mar 11, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Mar 2, 2026 | Mar 11, 2026 | Approved |
Building plan review Building Inspection · BLDG | Mar 9, 2026 | Mar 13, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Mar 9, 2026 | Mar 10, 2026 | Approved |
Building plan review Building Inspection · BLDG | Mar 17, 2026 | Mar 24, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Mar 17, 2026 | Mar 18, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 17, 2026 | Mar 23, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Mar 17, 2026 | Apr 3, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 17, 2026 | Mar 20, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 3, 2026 | Apr 9, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $347,771
| Name | Role | License on permit |
|---|---|---|
| Andrew Ross Levine Levine Architects | Architect | C14090 |
| Albert Urrutia Atrium Structural Engineer | Engineer | S2994 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026