1 Dr Carlton B Goodlett Pl
San Francisco permit 202510036737 · Tenderloin
Prop h:tenant improvement of(e)childcare area within city hall @ ground fl
- Filed
- Oct 3, 2025
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 25 stops across 5 departments
- Comments issued
- 8 times, by Building Inspection, Fire Department, Planning
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Oct 3, 2025 | Oct 3, 2025 | Administrative |
Permit Processing Center Building Inspection · PPC | Oct 3, 2025 | Dec 24, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Oct 6, 2025 | Oct 9, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Oct 6, 2025 | Oct 7, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Oct 7, 2025 | Oct 7, 2025 | Approved |
Building plan review Building Inspection · BLDG | Oct 9, 2025 | Oct 21, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 15, 2025 | Oct 15, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Oct 20, 2025 | Oct 20, 2025 | Approved |
Zoning review Planning · CP-ZOC | Oct 22, 2025 | Oct 22, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 17, 2025 | Nov 21, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Nov 17, 2025 | Nov 17, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 17, 2025 | Nov 17, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 20, 2025 | Nov 20, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Nov 20, 2025 | Nov 20, 2025 | Approved |
Zoning review Planning · CP-ZOC | Nov 25, 2025 | Nov 25, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Nov 25, 2025 | Nov 25, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Nov 26, 2025 | Nov 26, 2025 | Approved |
Building plan review Building Inspection · BLDG | Dec 10, 2025 | Dec 24, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Dec 10, 2025 | Dec 10, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 10, 2025 | Dec 11, 2025 | Approved |
Zoning review Planning · CP-ZOC | Dec 11, 2025 | Dec 11, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 11, 2025 | Dec 11, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Dec 12, 2025 | Dec 12, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 15, 2025 | Dec 15, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 24, 2025 | In progress | In Progress |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Filed
- Estimated cost
- $1,100,000
| Name | Role | License on permit |
|---|---|---|
| Christopher J Dorman Dorman Assoc | Architect | C28300 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2019