2238 Geary Bl
San Francisco permit 202510066816 · Japantown
Relocate nitrogen starage tank & asscociated components from rm 4w265 4th/f, 02w262 5th/f, & 06e262 6th/f to rm 1w135 1st/f. patch, paint, repair flooring after removal of the nitrogen tanks. remodel rm 1w135 1st/f to install nitrogen tank & associated component
- Filed
- Oct 6, 2025
- Issued
- Nov 20, 2025 (1 month after filing)
- Completed
- Sep 23, 2026 (10 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2025 were typically issued within 1 month (median of 5,178 issued permits).
- Review stops
- 12 stops across 4 departments
- Comments issued
- 3 times, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Oct 6, 2025 | Oct 6, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Oct 6, 2025 | Oct 6, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Oct 6, 2025 | Oct 6, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 7, 2025 | Oct 7, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 7, 2025 | Oct 7, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Oct 7, 2025 | Oct 7, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Oct 7, 2025 | Oct 7, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Nov 10, 2025 | Nov 10, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Nov 10, 2025 | Nov 10, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 12, 2025 | Nov 12, 2025 | Approved |
Public health review Public Health · HEALTH | Nov 12, 2025 | Nov 12, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 20, 2025 | Nov 20, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $50,000
| Name | Role | License on permit |
|---|---|---|
| Scott Alan Jensen | Architect | C40292 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026