281 A Castro St
San Francisco permit 202510076859 · Castro/Upper Market
Legalization of (e) studio unit to comply with nov 202182222: interior remodel to create adu at 1/f level of (e) 3-story, 2-unit.
- Filed
- Oct 21, 2025
- Issued
- Jan 16, 2026 (3 months after filing)
- Completed
- May 13, 2026 (4 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 20 stops across 6 departments
- Comments issued
- Twice, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Oct 3, 2025 | Oct 14, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 21, 2025 | Oct 21, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Oct 21, 2025 | Oct 29, 2025 | Approved |
Building plan review Building Inspection · BLDG | Oct 21, 2025 | Oct 28, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 21, 2025 | Oct 24, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 21, 2025 | Oct 23, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 21, 2025 | Oct 22, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Oct 21, 2025 | Nov 4, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 21, 2025 | Oct 30, 2025 | Approved |
Building inspector Building Inspection · BID-INSP | Oct 21, 2025 | Nov 21, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Oct 21, 2025 | Dec 2, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Nov 18, 2025 | Dec 2, 2025 | Approved |
Building plan review Building Inspection · BLDG | Nov 18, 2025 | Nov 21, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 18, 2025 | Nov 25, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Nov 18, 2025 | Nov 20, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 18, 2025 | Nov 20, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Nov 18, 2025 | Dec 2, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 18, 2025 | Dec 1, 2025 | Approved |
Development fee collection Building Inspection · DFCU | Dec 2, 2025 | Dec 2, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Dec 2, 2025 | Jan 16, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $128,175
| Name | Role | License on permit |
|---|---|---|
| Andrea Gabriele Cernusak Andrea Cernusak | Architect | C33206 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2022