460 Fair Oaks St

San Francisco permit 202510076898 · Mission

Addition (type unconfirmed)Full plan reviewIssued
Street view · Sep 2026
Google Street View of 460 Fair Oaks St, Sep 2026
Scope of work
As written on the permit application.

Expand unit on level 1 (#462a) to add a bathroom and relocate bedrooms. interior remodel/reconfigure level 2 (#460) & level 3 (#462). add new 297 sqft roof deck.

Timeline
Key dates from the city record.
Filed
Dec 1, 2025
Issued
May 7, 2026 (5 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
25 stops across 5 departments
Comments issued
6 times, by Building Inspection, Fire Department
Review stopFinishedResult

Apartment and hotel inspection

Building Inspection · HIS

Oct 7, 2025Approved

Intake

Building Inspection · INTAKE

Oct 7, 2025Administrative

Zoning review

Planning · CP-ZOC

Oct 10, 2025Approved

Permit Center

Permit Center · PERMIT-CTR

Nov 19, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Dec 2, 2025Administrative

Zoning review

Planning · CP-ZOC

Dec 30, 2025Approved

Building plan review

Building Inspection · BLDG

Dec 26, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Jan 8, 2026Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jan 5, 2026Issued Comments

Fire prevention review

Fire Department · SFFD

Jan 22, 2026Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Dec 18, 2025Approved

Permit Processing Center

Building Inspection · PPC

Apr 24, 2026Administrative

Building plan review

Building Inspection · BLDG

Mar 31, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

Feb 12, 2026Issued Comments

Building plan review quality control

Building Inspection · BLDG-QC

Feb 18, 2026Approved

Structural plan approval

Building Inspection · PAD-STR

Feb 17, 2026Approved

Fire prevention review

Fire Department · SFFD

Feb 24, 2026Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Mar 2, 2026Approved

Fire prevention review

Fire Department · SFFD

Apr 7, 2026Approved

Structural plan approval

Building Inspection · PAD-STR

Mar 31, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

Mar 17, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

Mar 30, 2026Approved

Zoning review

Planning · CP-ZOC

Apr 16, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

Apr 22, 2026Approved

Central Permit Bureau

Building Inspection · CPB

May 7, 2026Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$1,383,232
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Michael William Terndrup

Eag Studio Architecture

ArchitectC40160
Humza Shahid Chowdhry

Humza Chowdhry

EngineerS6091
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202510076898 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record