2533 24th Av
San Francisco permit 202510086938 · Sunset/Parkside
New state adu - 2 beds,2 baths on g/f including rear extension. remodel of (e) main unit to inlcude 3rd floor addition and rear extension.
- Filed
- Oct 16, 2025
- Issued
- May 5, 2026 (7 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 27 stops across 6 departments
- Comments issued
- 5 times, by Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Oct 7, 2025 | Oct 14, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 16, 2025 | Oct 16, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Oct 16, 2025 | Nov 12, 2025 | Approved |
Building plan review Building Inspection · BLDG | Oct 16, 2025 | Nov 6, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Oct 16, 2025 | Nov 6, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Oct 16, 2025 | Nov 5, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 16, 2025 | Oct 17, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 16, 2025 | Oct 20, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Oct 16, 2025 | Nov 14, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Oct 16, 2025 | Oct 24, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Oct 16, 2025 | Apr 9, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jan 9, 2026 | Jan 9, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 9, 2026 | Feb 3, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 9, 2026 | Jan 12, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 9, 2026 | Jan 22, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 9, 2026 | Jan 12, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jan 9, 2026 | Jan 23, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 9, 2026 | Jan 13, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 24, 2026 | Feb 25, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Feb 26, 2026 | Apr 1, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 27, 2026 | Feb 27, 2026 | Approved |
Zoning review Planning · CP-ZOC | Mar 2, 2026 | Mar 2, 2026 | Approved |
Building plan review Building Inspection · BLDG | Mar 11, 2026 | Mar 11, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 6, 2026 | Apr 8, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Apr 8, 2026 | Apr 9, 2026 | Approved |
Development fee collection Building Inspection · DFCU | Apr 8, 2026 | Apr 8, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Apr 9, 2026 | May 5, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $995,305
| Name | Role | License on permit |
|---|---|---|
| Roger M Wong Live Architects | Architect | C26423 |
| Marcus Yan Sf Bay Engineering | Engineer | C83553 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Nov 2020