500 Terry A Francois Bl
San Francisco permit 202510147300 · Mission Bay
Ground floor ti work includes refresh of tenant spaces north and main lobby and full ti to suite soth main lobby. partitions, fixtures and finishes and associated mep
- Filed
- Oct 14, 2025
- Issued
- Feb 24, 2026 (4 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2025 were typically issued within 1 month (median of 5,178 issued permits).
- Review stops
- 17 stops across 4 departments
- Comments issued
- 4 times, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Oct 14, 2025 | Oct 14, 2025 | Administrative |
Electrical plan review Building Inspection · MECH-E | Oct 15, 2025 | Oct 15, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 15, 2025 | Oct 15, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 18, 2025 | Nov 18, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Nov 18, 2025 | Nov 18, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Nov 18, 2025 | Nov 18, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Nov 18, 2025 | Nov 18, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Jan 6, 2026 | Jan 6, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 8, 2026 | Jan 8, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 9, 2026 | Jan 9, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jan 9, 2026 | Jan 9, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 26, 2026 | Jan 26, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 28, 2026 | Jan 28, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 11, 2026 | Feb 11, 2026 | Approved |
Redevelopment review Redevelopment · REDEV | Feb 11, 2026 | Feb 11, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Feb 12, 2026 | Feb 12, 2026 | Approved-Stipulated |
Central Permit Bureau Building Inspection · CPB | Feb 24, 2026 | Feb 24, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $5,263,755
| Name | Role | License on permit |
|---|---|---|
| Matthew Richard Usbeck | Architect | C-33171 |
| Paul Anthony Littler Holmes Structural | Engineer | S6189 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jun 2017