6100 Geary Bl
San Francisco permit 202510147340 · Outer Richmond
Voluntary seismic upgrade of (e) retail banking space,requiring full removal & reconstruction of (e) ti conditions, including mep, (e) tenant to remain, no change in use, no change in building area.
- Filed
- Dec 5, 2025
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 26 stops across 5 departments
- Comments issued
- 5 times, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Oct 9, 2025 | Oct 20, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 21, 2025 | Dec 5, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Dec 5, 2025 | Dec 11, 2025 | Approved |
Building plan review Building Inspection · BLDG | Dec 5, 2025 | Jan 20, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Dec 5, 2025 | Jan 28, 2026 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Dec 5, 2025 | Jan 9, 2026 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Dec 5, 2025 | Dec 9, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Dec 5, 2025 | Dec 9, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 5, 2025 | Dec 16, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Dec 5, 2025 | In progress | — |
Building plan review quality control Building Inspection · BLDG-QC | Jan 21, 2026 | Jan 27, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Feb 18, 2026 | Feb 19, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 24, 2026 | Feb 25, 2026 | Issued Comments |
Zoning review Planning · CP-ZOC | Oct 6, 2026 | Oct 7, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | Oct 6, 2026 | Oct 28, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 7, 2026 | Oct 14, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 9, 2026 | Oct 19, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 13, 2026 | Oct 13, 2026 | Approved |
Building plan review Building Inspection · BLDG | Oct 20, 2026 | Oct 20, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 2, 2026 | Nov 2, 2026 | Approved |
Zoning review Planning · CP-ZOC | Nov 3, 2026 | Nov 3, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 3, 2026 | In progress | — |
Electrical plan review Building Inspection · MECH-E | Nov 3, 2026 | Nov 3, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 3, 2026 | Nov 4, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 3, 2026 | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $2,000,000
| Name | Role | License on permit |
|---|---|---|
| Shawn M Anderson Msa Architecture | Architect | C31273 |
| Ramon Gilsanz | Engineer | S4161 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2022