57 Carmelita St
San Francisco permit 202510157458 · Haight Ashbury
Lower slab at ground level for new garage and additional dwelling, storage and mechanical space. install front yard garage ramp and planters. remodel main level (level 1) new kitchen and garden room. remove (e) garden room. remodel upper level (level 2) new primary bath.
- Filed
- Dec 1, 2025
- Issued
- Mar 27, 2026 (4 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 19 stops across 6 departments
- Comments issued
- 6 times, by Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Oct 9, 2025 | Oct 23, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 24, 2025 | Dec 2, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Dec 2, 2025 | Mar 23, 2026 | Approved |
Building plan review Building Inspection · BLDG | Dec 2, 2025 | Jan 16, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Dec 2, 2025 | Jan 5, 2026 | Not Applicable |
Mechanical and energy plan review Building Inspection · MECH | Dec 2, 2025 | Dec 17, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 2, 2025 | Dec 3, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Dec 2, 2025 | Dec 10, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Dec 2, 2025 | Dec 22, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Dec 2, 2025 | Mar 24, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Feb 9, 2026 | Feb 19, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 9, 2026 | Feb 23, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Feb 9, 2026 | Feb 11, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Feb 9, 2026 | Feb 19, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Feb 9, 2026 | Feb 10, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Feb 17, 2026 | Feb 18, 2026 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Feb 17, 2026 | Feb 18, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 19, 2026 | Mar 19, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 24, 2026 | Mar 27, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $616,835
| Name | Role | License on permit |
|---|---|---|
| Matthias Troitzsch Id8bau | Architect | C30973 |
| Michael Austin Hom Hom & Pisano Engineering Inc. | Engineer | 71450 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jun 2025