Horizontal addition w/new rooms down to convert e) 3 bedroom, 1 bath house to a 4 bedroom & 3 bath house plus media rm. extending e) residence in 1=story addition into rear yard, infill north lightwell on upper level, partial infill lightwell on south side, both within neighbor approval.

Timeline
Key dates from the city record.
Filed
Oct 31, 2025
Issued
Mar 27, 2026 (5 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
24 stops across 6 departments
Comments issued
5 times, by Building Inspection, Public Works, Public Utilities
Review stopFinishedResult

Intake

Building Inspection · INTAKE

Oct 16, 2025Administrative

Zoning review

Planning · CP-ZOC

Oct 16, 2025Approved

Permit Center

Permit Center · PERMIT-CTR

Oct 27, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Oct 31, 2025Administrative

Zoning review

Planning · CP-ZOC

Nov 3, 2025Approved

Building plan review

Building Inspection · BLDG

Dec 24, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Dec 24, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Nov 25, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

Nov 6, 2025Approved-Stipulated

Street use and mapping

Public Works · DPW-BSM

Nov 4, 2025Issued Comments

Urban forestry

Public Works · DPW-BUF

Nov 26, 2025Approved-Stipulated

Public Utilities Commission review

Public Utilities · SFPUC

Nov 13, 2025Issued Comments

Permit Processing Center

Building Inspection · PPC

Feb 23, 2026Administrative

Public Utilities Commission review

Public Utilities · SFPUC

Nov 14, 2025Approved

Zoning review

Planning · CP-ZOC

Feb 4, 2026Approved

Building plan review

Building Inspection · BLDG

Feb 9, 2026Approved

Structural plan approval

Building Inspection · PAD-STR

Feb 9, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

Feb 11, 2026Approved

Fire prevention review

Fire Department · SFFD

Feb 6, 2026Approved-Stipulated

Street use and mapping

Public Works · DPW-BSM

Feb 6, 2026Approved

Urban forestry

Public Works · DPW-BUF

Feb 22, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

Feb 6, 2026Approved

Building plan review quality control

Building Inspection · BLDG-QC

Feb 9, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Mar 27, 2026Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$716,033
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Anne Clark Forell

Anne Forell Architecture

ArchitectC27146
Shaun Edward Moynahan

Semco Engineering

EngineerS4605
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202510167514 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record