534 18th Av
San Francisco permit 202510177605 · Outer Richmond
Comply with nov 202316929 horizontal three story addition at rear. add 2 bed and 1.5 bath & entertainment, wet bar with 2 elec burner, expand kitchen and dinning room, add shower on 2nd fl. remove bed room on 3rd fl. add one bathroom on 3rd fl. remove deck at rear item number 4.
- Filed
- Dec 8, 2025
- Issued
- Mar 16, 2026 (3 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 31 stops across 6 departments
- Comments issued
- 4 times, by Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Oct 17, 2025 | Oct 17, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Oct 17, 2025 | Oct 28, 2025 | Approved |
Zoning review Planning · CP-ZOC | Oct 28, 2025 | Oct 28, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Oct 31, 2025 | Oct 31, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 6, 2025 | Nov 6, 2025 | Approved |
Building plan review Building Inspection · BLDG | Nov 7, 2025 | Nov 7, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Nov 7, 2025 | Nov 7, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 7, 2025 | Nov 7, 2025 | Approved |
Permit Center Permit Center · PERMIT-CTR | Nov 13, 2025 | Dec 3, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 4, 2025 | Dec 8, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Dec 8, 2025 | Dec 15, 2025 | Approved |
Building plan review Building Inspection · BLDG | Dec 8, 2025 | Feb 9, 2026 | Not Applicable |
Structural plan approval Building Inspection · PAD-STR | Dec 8, 2025 | Jan 16, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 8, 2025 | Jan 7, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Dec 8, 2025 | Dec 15, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 8, 2025 | Dec 9, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Dec 8, 2025 | Jan 7, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 8, 2025 | Dec 9, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Dec 8, 2025 | Mar 4, 2026 | Administrative |
Building plan review quality control Building Inspection · BLDG-QC | Jan 15, 2026 | Jan 15, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 16, 2026 | Jan 16, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 9, 2026 | Feb 17, 2026 | Approved |
Zoning review Planning · CP-ZOC | Feb 9, 2026 | Feb 10, 2026 | Approved |
Building plan review Building Inspection · BLDG | Feb 9, 2026 | Feb 9, 2026 | Not Applicable |
Structural plan approval Building Inspection · PAD-STR | Feb 9, 2026 | Feb 19, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 9, 2026 | Feb 19, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Feb 9, 2026 | Feb 11, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 9, 2026 | Feb 11, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Feb 9, 2026 | Mar 2, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 9, 2026 | Feb 10, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 4, 2026 | Mar 16, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $482,533
| Name | Role | License on permit |
|---|---|---|
| Ronald Gate Yu Yuflux Engineering Llc. | Engineer | C76647 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2022