1262 46th Av
San Francisco permit 202510207736 · Sunset/Parkside
Erect a (n) type v-b, 3-story building with 2 residential units.
- Filed
- Dec 3, 2025
- Issued
- Apr 6, 2026 (4 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 28 stops across 6 departments
- Comments issued
- 7 times, by Permit Center, Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Oct 15, 2025 | Oct 24, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Nov 18, 2025 | Dec 2, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 3, 2025 | Dec 4, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Dec 4, 2025 | Jan 5, 2026 | Approved |
Building plan review Building Inspection · BLDG | Dec 4, 2025 | Dec 26, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Dec 4, 2025 | Dec 22, 2025 | Not Applicable |
Mechanical and energy plan review Building Inspection · MECH | Dec 4, 2025 | Dec 24, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 4, 2025 | Dec 8, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 4, 2025 | Dec 9, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Dec 4, 2025 | Dec 29, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Dec 4, 2025 | Dec 12, 2025 | Approved |
Public Utilities programs review Public Utilities · SFPUC-PRG | Dec 4, 2025 | Dec 29, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Dec 4, 2025 | Mar 26, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Jan 14, 2026 | Jan 22, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 14, 2026 | Jan 28, 2026 | Approved |
Zoning review Planning · CP-ZOC | Jan 27, 2026 | Jan 27, 2026 | Approved |
Building plan review Building Inspection · BLDG | Feb 9, 2026 | Feb 10, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 17, 2026 | Feb 23, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 24, 2026 | Mar 11, 2026 | Approved |
Zoning review Planning · CP-ZOC | Mar 13, 2026 | Mar 16, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 13, 2026 | Mar 16, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Mar 13, 2026 | Mar 19, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Mar 13, 2026 | Mar 13, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Mar 13, 2026 | Mar 13, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 13, 2026 | Mar 19, 2026 | Approved |
Public Utilities programs review Public Utilities · SFPUC-PRG | Mar 13, 2026 | Mar 19, 2026 | Approved |
Development fee collection Building Inspection · DFCU | Mar 24, 2026 | Mar 24, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Mar 26, 2026 | Apr 6, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Issued
- Estimated cost
- $953,505
| Name | Role | License on permit |
|---|---|---|
| Katherine Ann Fontaine Actually Design Build | Architect | C34740 |
| Kathryn Briggs Base Design | Engineer | 5732 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2025