41 Mallorca Wy
San Francisco permit 202510217768 · Marina
Convert existing ground floor storage to master suite. add warm board radiant heat, bathroom, new pell. all wood lifestyle windows in like kind of existing; remove any residual knob/tub replace with romex move electrical meters from rear to front near gas/ water. new sewer lateral & slab on grade
- Filed
- Oct 21, 2025
- Issued
- Nov 20, 2025 (1 month after filing)
- Completed
- Jul 21, 2026 (8 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2025 were typically issued within 1 month (median of 5,178 issued permits).
- Review stops
- 13 stops across 5 departments
- Comments issued
- Twice, by Planning, Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Oct 21, 2025 | Oct 21, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Oct 21, 2025 | Oct 21, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Oct 23, 2025 | Oct 23, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 23, 2025 | Oct 23, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Oct 23, 2025 | Oct 23, 2025 | Approved |
Intake Building Inspection · INTAKE | Nov 18, 2025 | Nov 18, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Nov 18, 2025 | Nov 18, 2025 | Approved |
Building plan review Building Inspection · BLDG | Nov 18, 2025 | Nov 18, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 20, 2025 | Nov 20, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Nov 20, 2025 | Nov 20, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 20, 2025 | Nov 20, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 20, 2025 | Nov 20, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 20, 2025 | Nov 20, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $95,625
| Name | Role | License on permit |
|---|---|---|
| Peter Petruzzi | Architect | C18480 |
| Donald David Double D Engineeering | Engineer | S-3928 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2022